Royal Regency Suites construction progress

The registered completion date for Royal Regency Suites in Business Bay is December 2026. At the last site inspection, in October 2026, it was 57% built. The developer is Alseeb Real Estate Development.

57%

Built, at the site inspection of 27 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
April 2029
Construction started
October 2023
First registered
January 2024
Developer
Alseeb Real Estate Development
Community
Business Bay
Units
238
Escrow bank
Dubai Islamic Bank
Name in Arabic
رويال ريجينسى سويتس
Project number
2792
Site inspections
12

Schedule

Between December 2025 and October 2026 the site added about 1.5 points a month. At that rate it would finish around April 2029, more than three months after its registered date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

57%+1.0 pts

  • Royal Regency Suites construction site, inspection photo 1, 27 October 2026
  • Royal Regency Suites construction site, inspection photo 2, 27 October 2026
  • Royal Regency Suites construction site, inspection photo 3, 27 October 2026
  • Royal Regency Suites construction site, inspection photo 4, 27 October 2026

19 August 2026

56%+2.6 pts

  • Royal Regency Suites construction site, inspection photo 1, 19 August 2026
  • Royal Regency Suites construction site, inspection photo 2, 19 August 2026
  • Royal Regency Suites construction site, inspection photo 3, 19 August 2026
  • Royal Regency Suites construction site, inspection photo 4, 19 August 2026

22 June 2026

54%+6.5 pts

  • Royal Regency Suites construction site, inspection photo 1, 22 June 2026
  • Royal Regency Suites construction site, inspection photo 2, 22 June 2026
  • Royal Regency Suites construction site, inspection photo 3, 22 June 2026
  • Royal Regency Suites construction site, inspection photo 4, 22 June 2026

23 March 2026

47%+4.8 pts

  • Royal Regency Suites construction site, inspection photo 1, 23 March 2026
  • Royal Regency Suites construction site, inspection photo 2, 23 March 2026
  • Royal Regency Suites construction site, inspection photo 3, 23 March 2026
  • Royal Regency Suites construction site, inspection photo 4, 23 March 2026

22 December 2025

42%+9.2 pts

  • Royal Regency Suites construction site, inspection photo 1, 22 December 2025
  • Royal Regency Suites construction site, inspection photo 2, 22 December 2025
  • Royal Regency Suites construction site, inspection photo 3, 22 December 2025
  • Royal Regency Suites construction site, inspection photo 4, 22 December 2025

29 August 2025

33%+4.8 pts

  • Royal Regency Suites construction site, inspection photo 1, 29 August 2025
  • Royal Regency Suites construction site, inspection photo 2, 29 August 2025
  • Royal Regency Suites construction site, inspection photo 3, 29 August 2025
  • Royal Regency Suites construction site, inspection photo 4, 29 August 2025

28 July 2025

28%+2.5 pts

  • Royal Regency Suites construction site, inspection photo 1, 28 July 2025
  • Royal Regency Suites construction site, inspection photo 2, 28 July 2025
  • Royal Regency Suites construction site, inspection photo 3, 28 July 2025
  • Royal Regency Suites construction site, inspection photo 4, 28 July 2025

17 June 2025

26%+5.4 pts

  • Royal Regency Suites construction site, inspection photo 1, 17 June 2025
  • Royal Regency Suites construction site, inspection photo 2, 17 June 2025
  • Royal Regency Suites construction site, inspection photo 3, 17 June 2025
  • Royal Regency Suites construction site, inspection photo 4, 17 June 2025

6 March 2025

20%+9.3 pts

  • Royal Regency Suites construction site, inspection photo 1, 6 March 2025
  • Royal Regency Suites construction site, inspection photo 2, 6 March 2025
  • Royal Regency Suites construction site, inspection photo 3, 6 March 2025
  • Royal Regency Suites construction site, inspection photo 4, 6 March 2025

18 December 2024

11%+1.7 pts

  • Royal Regency Suites construction site, inspection photo 1, 18 December 2024
  • Royal Regency Suites construction site, inspection photo 2, 18 December 2024
  • Royal Regency Suites construction site, inspection photo 3, 18 December 2024
  • Royal Regency Suites construction site, inspection photo 4, 18 December 2024

All 88 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Alseeb Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Royal Regency Suites?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Royal Regency Suites handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Royal Regency Suites?
Royal Regency Suites was 57% built at the site inspection on 27 October 2026. The site has been inspected 12 times since September 2023. The Land Department took 88 site photos at its inspections.
Is Royal Regency Suites delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Royal Regency Suites?
The registered developer is Alseeb Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Royal Regency Suites?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.