One River Point construction progress
The registered completion date for One River Point in Business Bay is June 2027. At the last site inspection, in November 2026, it was 48% built. The developer is Dutco Ellington Canal Front Real Estate.
48%
Built, at the site inspection of 17 November 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- August 2028
- Construction started
- October 2023
- First registered
- January 2024
- Developer
- Dutco Ellington Canal Front Real Estate
- Community
- Business Bay
- Units
- 298
- Escrow bank
- Emirates NBD
- Name in Arabic
- ون ريفر بوينت
- Project number
- 2929
- Site inspections
- 5
Schedule
Between March 2026 and November 2026 the site added about 2.5 points a month. At that rate it would finish around August 2028, more than three months after its registered date of June 2027.
Site inspections
17 November 2026
48%+12 pts
21 July 2026
35%+6.6 pts
27 March 2026
29%+17 pts
18 July 2025
12%+12 pts
12 January 2024
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in One River Point?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the One River Point handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on One River Point?
- One River Point was 48% built at the site inspection on 17 November 2026. The site has been inspected 5 times since January 2024. The Land Department took 46 site photos at its inspections.
- Is One River Point delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building One River Point?
- The registered developer is Dutco Ellington Canal Front Real Estate.
- Which bank holds the escrow account for One River Point?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)