Downtown Residences construction progress
The registered completion date for Downtown Residences in Business Bay is December 2030. At the last site inspection, in September 2026, it was 1.3% built. The developer is Deyaar Development.
1.3%
Built, at the site inspection of 24 September 2026
Running behind its date
- Registered completion date
- December 2030
- Finish at recent pace
- October 2153
- Construction started
- December 2025
- First registered
- June 2025
- Developer
- Deyaar Development
- Community
- Business Bay
- Units
- 524
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- داون تاون ريزيدنسيس
- Project number
- 3777
- Site inspections
- 3
Schedule
Between June 2026 and September 2026 the site added about 0.1 points a month. At that rate it would finish around October 2153, more than three months after its registered date of December 2030.
Site inspections
24 September 2026
1.3%+0.2 pts
22 June 2026
1.1%+1.1 pts
19 May 2025
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Deyaar Development has 9 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Downtown Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Downtown Residences handover date?
- The registered completion date is December 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2153. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Downtown Residences?
- Downtown Residences was 1.3% built at the site inspection on 24 September 2026. The site has been inspected 3 times since May 2025. The Land Department took 12 site photos at its inspections.
- Is Downtown Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2030.
- Who is building Downtown Residences?
- The registered developer is Deyaar Development. It has 8 other projects under construction in Dubai.
- Which bank holds the escrow account for Downtown Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mar CasaAlso by Deyaar Development. 67%, Due October 2026, passed.
- Rosalia ResidencesAlso by Deyaar Development. 93%.
- Eleve By DeyaarAlso by Deyaar Development. 20%.
- Elm At Park FiveAlso by Deyaar Development. 16%, Due June 2027.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)