Chic Tower construction progress

Chic Tower in Business Bay was registered to complete in July 2025 and is still under construction. At the last site inspection, in August 2026, it was 84% built. The developer is Pax Investment.

84%

Built, at the site inspection of 17 August 2026

16 months past its registered completion date

Registered completion date
July 2025
Finish at recent pace
January 2027
Construction started
March 2023
First registered
October 2022
Developer
Pax Investment
Community
Business Bay
Units
467
Escrow bank
Mashreq Bank
Name in Arabic
شييك تاور
Project number
2460
Site inspections
11

Schedule

Chic Tower was registered to complete in July 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

84%+10 pts

  • Chic Tower construction site, inspection photo 1, 17 August 2026
  • Chic Tower construction site, inspection photo 2, 17 August 2026
  • Chic Tower construction site, inspection photo 3, 17 August 2026
  • Chic Tower construction site, inspection photo 4, 17 August 2026

8 April 2026

74%+15 pts

  • Chic Tower construction site, inspection photo 1, 8 April 2026
  • Chic Tower construction site, inspection photo 2, 8 April 2026
  • Chic Tower construction site, inspection photo 3, 8 April 2026
  • Chic Tower construction site, inspection photo 4, 8 April 2026

11 December 2025

59%+11 pts

  • Chic Tower construction site, inspection photo 1, 11 December 2025
  • Chic Tower construction site, inspection photo 2, 11 December 2025
  • Chic Tower construction site, inspection photo 3, 11 December 2025
  • Chic Tower construction site, inspection photo 4, 11 December 2025

4 August 2025

48%+18 pts

  • Chic Tower construction site, inspection photo 1, 4 August 2025
  • Chic Tower construction site, inspection photo 2, 4 August 2025
  • Chic Tower construction site, inspection photo 3, 4 August 2025
  • Chic Tower construction site, inspection photo 4, 4 August 2025

10 April 2025

30%+11 pts

  • Chic Tower construction site, inspection photo 1, 10 April 2025
  • Chic Tower construction site, inspection photo 2, 10 April 2025
  • Chic Tower construction site, inspection photo 3, 10 April 2025
  • Chic Tower construction site, inspection photo 4, 10 April 2025

21 January 2025

19%+3.8 pts

  • Chic Tower construction site, inspection photo 1, 21 January 2025
  • Chic Tower construction site, inspection photo 2, 21 January 2025
  • Chic Tower construction site, inspection photo 3, 21 January 2025
  • Chic Tower construction site, inspection photo 4, 21 January 2025

5 July 2024

15%+7.6 pts

  • Chic Tower construction site, inspection photo 1, 5 July 2024
  • Chic Tower construction site, inspection photo 2, 5 July 2024

14 March 2024

7.3%+3.3 pts

  • Chic Tower construction site, inspection photo 1, 14 March 2024
  • Chic Tower construction site, inspection photo 2, 14 March 2024
  • Chic Tower construction site, inspection photo 3, 14 March 2024
  • Chic Tower construction site, inspection photo 4, 14 March 2024

9 August 2023

4.0%+3.9 pts

  • Chic Tower construction site, inspection photo 1, 9 August 2023
  • Chic Tower construction site, inspection photo 2, 9 August 2023
  • Chic Tower construction site, inspection photo 3, 9 August 2023
  • Chic Tower construction site, inspection photo 4, 9 August 2023

11 April 2023

0.1%+0.1 pts

  • Chic Tower construction site, inspection photo 1, 11 April 2023
  • Chic Tower construction site, inspection photo 2, 11 April 2023
  • Chic Tower construction site, inspection photo 3, 11 April 2023
  • Chic Tower construction site, inspection photo 4, 11 April 2023

All 62 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Chic Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Chic Tower handover date?
The registered completion date was July 2025, and the register still lists Chic Tower as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Chic Tower?
Chic Tower was 84% built at the site inspection on 17 August 2026. The site has been inspected 11 times since September 2022. The Land Department took 62 site photos at its inspections.
Is Chic Tower delayed?
Yes. Its registered completion date of July 2025 has passed and the project is still listed as under construction.
Who is building Chic Tower?
The registered developer is Pax Investment.
Which bank holds the escrow account for Chic Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.