Chic Tower construction progress
Chic Tower in Business Bay was registered to complete in July 2025 and is still under construction. At the last site inspection, in August 2026, it was 84% built. The developer is Pax Investment.
84%
Built, at the site inspection of 17 August 2026
16 months past its registered completion date
- Registered completion date
- July 2025
- Finish at recent pace
- January 2027
- Construction started
- March 2023
- First registered
- October 2022
- Developer
- Pax Investment
- Community
- Business Bay
- Units
- 467
- Escrow bank
- Mashreq Bank
- Name in Arabic
- شييك تاور
- Project number
- 2460
- Site inspections
- 11
Schedule
Chic Tower was registered to complete in July 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 3.1 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
17 August 2026
84%+10 pts
8 April 2026
74%+15 pts
11 December 2025
59%+11 pts
4 August 2025
48%+18 pts
10 April 2025
30%+11 pts
21 January 2025
19%+3.8 pts
5 July 2024
15%+7.6 pts
14 March 2024
7.3%+3.3 pts
9 August 2023
4.0%+3.9 pts
11 April 2023
0.1%+0.1 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Chic Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Chic Tower handover date?
- The registered completion date was July 2025, and the register still lists Chic Tower as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Chic Tower?
- Chic Tower was 84% built at the site inspection on 17 August 2026. The site has been inspected 11 times since September 2022. The Land Department took 62 site photos at its inspections.
- Is Chic Tower delayed?
- Yes. Its registered completion date of July 2025 has passed and the project is still listed as under construction.
- Who is building Chic Tower?
- The registered developer is Pax Investment.
- Which bank holds the escrow account for Chic Tower?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)









.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)