77s construction progress
The registered completion date for 77s in Business Bay is December 2028. At the last site inspection, in September 2026, it was 14% built. The developer is 77 Shades Of Green Realestate Development.
14%
Built, at the site inspection of 10 September 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- June 2423
- Construction started
- January 2025
- First registered
- January 2025
- Developer
- 77 Shades Of Green Realestate Development
- Community
- Business Bay
- Units
- 405
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- 77س
- Project number
- 274
- Site inspections
- 7
Schedule
Between June 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around June 2423, more than three months after its registered date of December 2028.
Site inspections
10 September 2026
14%+0.1 pts
18 June 2026
14%
27 May 2019
14%+0.2 pts
6 December 2018
14%+1.5 pts
30 March 2015
12%+1.6 pts
25 February 2014
11%
22 May 2013
11%
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in 77s?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 77s handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2423. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 77s?
- 77s was 14% built at the site inspection on 10 September 2026. The site has been inspected 7 times since May 2013. The Land Department took 41 site photos at its inspections.
- Is 77s delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building 77s?
- The registered developer is 77 Shades Of Green Realestate Development.
- Which bank holds the escrow account for 77s?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.