77s construction progress
77s in Business Bay is 14% built at the Land Department inspection of September 2026. Developer 77 Shades Of Green Realestate Development. Completion registered for December 2028.
14%
Built, at the Land Department site inspection of 10 September 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- June 2423
- Construction started
- January 2025
- Registered with the Land Department
- January 2025
- Developer
- 77 Shades Of Green Realestate Development
- Community
- Business Bay
- Units
- 405
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- 77س
- Land Department project number
- 274
- Land Department site inspections
- 7
Schedule
Between June 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around June 2423, more than three months after the December 2028 date registered with the Land Department.
Site inspections
10 September 2026
14%+0.1 pts
18 June 2026
14%
27 May 2019
14%+0.2 pts
6 December 2018
14%+1.5 pts
30 March 2015
12%+1.6 pts
25 February 2014
11%
22 May 2013
11%
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in 77s?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will 77s be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around June 2423. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of 77s is built?
- 14%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 7 times since May 2013.
- Is 77s delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building 77s?
- The registered developer is 77 Shades Of Green Realestate Development.
- Which bank holds the escrow account for 77s?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.