77s construction progress

77s in Business Bay is 14% built at the Land Department inspection of September 2026. Developer 77 Shades Of Green Realestate Development. Completion registered for December 2028.

14%

Built, at the Land Department site inspection of 10 September 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
June 2423
Construction started
January 2025
Registered with the Land Department
January 2025
Developer
77 Shades Of Green Realestate Development
Community
Business Bay
Units
405
Escrow bank
Sharjah Islamic Bank
Name in Arabic
77س
Land Department project number
274
Land Department site inspections
7

Schedule

Between June 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around June 2423, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%20142017202020232026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 September 2026

14%+0.1 pts

  • 77s construction site, Land Department inspection photo 1, 10 September 2026
  • 77s construction site, Land Department inspection photo 2, 10 September 2026
  • 77s construction site, Land Department inspection photo 3, 10 September 2026
  • 77s construction site, Land Department inspection photo 4, 10 September 2026

18 June 2026

14%

  • 77s construction site, Land Department inspection photo 1, 18 June 2026
  • 77s construction site, Land Department inspection photo 2, 18 June 2026
  • 77s construction site, Land Department inspection photo 3, 18 June 2026
  • 77s construction site, Land Department inspection photo 4, 18 June 2026

27 May 2019

14%+0.2 pts

  • 77s construction site, Land Department inspection photo 1, 27 May 2019
  • 77s construction site, Land Department inspection photo 2, 27 May 2019
  • 77s construction site, Land Department inspection photo 3, 27 May 2019
  • 77s construction site, Land Department inspection photo 4, 27 May 2019

6 December 2018

14%+1.5 pts

  • 77s construction site, Land Department inspection photo 1, 6 December 2018
  • 77s construction site, Land Department inspection photo 2, 6 December 2018
  • 77s construction site, Land Department inspection photo 3, 6 December 2018
  • 77s construction site, Land Department inspection photo 4, 6 December 2018

30 March 2015

12%+1.6 pts

  • 77s construction site, Land Department inspection photo 1, 30 March 2015
  • 77s construction site, Land Department inspection photo 2, 30 March 2015
  • 77s construction site, Land Department inspection photo 3, 30 March 2015
  • 77s construction site, Land Department inspection photo 4, 30 March 2015

25 February 2014

11%

  • 77s construction site, Land Department inspection photo 1, 25 February 2014
  • 77s construction site, Land Department inspection photo 2, 25 February 2014
  • 77s construction site, Land Department inspection photo 3, 25 February 2014
  • 77s construction site, Land Department inspection photo 4, 25 February 2014

22 May 2013

11%

  • 77s construction site, Land Department inspection photo 1, 22 May 2013
  • 77s construction site, Land Department inspection photo 2, 22 May 2013
  • 77s construction site, Land Department inspection photo 3, 22 May 2013
  • 77s construction site, Land Department inspection photo 4, 22 May 2013

All 41 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in 77s?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will 77s be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around June 2423. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of 77s is built?
14%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 7 times since May 2013.
Is 77s delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building 77s?
The registered developer is 77 Shades Of Green Realestate Development.
Which bank holds the escrow account for 77s?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.