West Bay Tower construction progress

West Bay Tower in Business Bay is 83% built at the Land Department inspection of April 2026. Developer Orion Real Estate Development. Completion registered for February 2024.

83%

Built, at the Land Department site inspection of 20 April 2026

32 months past its registered completion date

Completion date (Land Department)
February 2024
Finish at recent pace
February 2028
Construction started
January 2016
Registered with the Land Department
December 2015
Developer
Orion Real Estate Development
Community
Business Bay
Units
253
Escrow bank
Emirates Islamic Bank
Name in Arabic
ويست باي تاور
Land Department project number
1701
Land Department site inspections
23

Schedule

West Bay Tower was registered to complete in February 2024, 32 months ago, and is still under construction. Over the last year of inspections it has added about 0.8 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%20172019202120232025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 April 2026

83%+4.0 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 20 April 2026
  • West Bay Tower construction site, Land Department inspection photo 2, 20 April 2026
  • West Bay Tower construction site, Land Department inspection photo 3, 20 April 2026
  • West Bay Tower construction site, Land Department inspection photo 4, 20 April 2026

28 January 2026

78%+1.9 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 28 January 2026
  • West Bay Tower construction site, Land Department inspection photo 2, 28 January 2026
  • West Bay Tower construction site, Land Department inspection photo 3, 28 January 2026
  • West Bay Tower construction site, Land Department inspection photo 4, 28 January 2026

11 September 2025

77%+14 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 11 September 2025
  • West Bay Tower construction site, Land Department inspection photo 2, 11 September 2025
  • West Bay Tower construction site, Land Department inspection photo 3, 11 September 2025
  • West Bay Tower construction site, Land Department inspection photo 4, 11 September 2025

11 April 2025

62%+5.1 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 11 April 2025
  • West Bay Tower construction site, Land Department inspection photo 2, 11 April 2025
  • West Bay Tower construction site, Land Department inspection photo 3, 11 April 2025
  • West Bay Tower construction site, Land Department inspection photo 4, 11 April 2025

11 November 2024

57%+9.2 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 11 November 2024
  • West Bay Tower construction site, Land Department inspection photo 2, 11 November 2024
  • West Bay Tower construction site, Land Department inspection photo 3, 11 November 2024
  • West Bay Tower construction site, Land Department inspection photo 4, 11 November 2024

13 February 2024

48%+9.5 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 13 February 2024
  • West Bay Tower construction site, Land Department inspection photo 2, 13 February 2024
  • West Bay Tower construction site, Land Department inspection photo 3, 13 February 2024
  • West Bay Tower construction site, Land Department inspection photo 4, 13 February 2024

1 August 2023

39%+4.6 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 1 August 2023
  • West Bay Tower construction site, Land Department inspection photo 2, 1 August 2023
  • West Bay Tower construction site, Land Department inspection photo 3, 1 August 2023
  • West Bay Tower construction site, Land Department inspection photo 4, 1 August 2023

17 March 2023

34%+3.8 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 17 March 2023
  • West Bay Tower construction site, Land Department inspection photo 2, 17 March 2023
  • West Bay Tower construction site, Land Department inspection photo 3, 17 March 2023
  • West Bay Tower construction site, Land Department inspection photo 4, 17 March 2023

24 November 2022

30%+2.9 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 24 November 2022
  • West Bay Tower construction site, Land Department inspection photo 2, 24 November 2022
  • West Bay Tower construction site, Land Department inspection photo 3, 24 November 2022
  • West Bay Tower construction site, Land Department inspection photo 4, 24 November 2022

20 July 2022

27%+2.1 pts

  • West Bay Tower construction site, Land Department inspection photo 1, 20 July 2022
  • West Bay Tower construction site, Land Department inspection photo 2, 20 July 2022
  • West Bay Tower construction site, Land Department inspection photo 3, 20 July 2022
  • West Bay Tower construction site, Land Department inspection photo 4, 20 July 2022

All 154 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in West Bay Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will West Bay Tower be completed?
The completion date registered with the Dubai Land Department is February 2024. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of West Bay Tower is built?
83%, measured at the Land Department site inspection on 20 April 2026. The Land Department engineers have inspected the site 23 times since October 2016.
Is West Bay Tower delayed?
Yes. Its registered completion date of February 2024 has passed and the Land Department still lists it as under construction.
Who is building West Bay Tower?
The registered developer is Orion Real Estate Development.
Which bank holds the escrow account for West Bay Tower?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.