West Bay Tower construction progress
West Bay Tower in Business Bay was registered to complete in February 2024 and is still under construction. At the last site inspection, in April 2026, it was 83% built. The developer is Orion Real Estate Development.
83%
Built, at the site inspection of 20 April 2026
34 months past its registered completion date
- Registered completion date
- February 2024
- Finish at recent pace
- February 2028
- Construction started
- January 2016
- First registered
- December 2015
- Developer
- Orion Real Estate Development
- Community
- Business Bay
- Units
- 253
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ويست باي تاور
- Project number
- 1701
- Site inspections
- 23
Schedule
West Bay Tower was registered to complete in February 2024, 34 months ago, and is still under construction. Over the last year of inspections it has added about 0.8 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
20 April 2026
83%+4.0 pts
28 January 2026
78%+1.9 pts
11 September 2025
77%+14 pts
11 April 2025
62%+5.1 pts
11 November 2024
57%+9.2 pts
13 February 2024
48%+9.5 pts
1 August 2023
39%+4.6 pts
17 March 2023
34%+3.8 pts
24 November 2022
30%+2.9 pts
20 July 2022
27%+2.1 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in West Bay Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the West Bay Tower handover date?
- The registered completion date was February 2024, and the register still lists West Bay Tower as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on West Bay Tower?
- West Bay Tower was 83% built at the site inspection on 20 April 2026. The site has been inspected 23 times since October 2016. The Land Department took 154 site photos at its inspections.
- Is West Bay Tower delayed?
- Yes. Its registered completion date of February 2024 has passed and the project is still listed as under construction.
- Who is building West Bay Tower?
- The registered developer is Orion Real Estate Development.
- Which bank holds the escrow account for West Bay Tower?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)










.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)