West Bay Tower construction progress
West Bay Tower in Business Bay is 83% built at the Land Department inspection of April 2026. Developer Orion Real Estate Development. Completion registered for February 2024.
83%
Built, at the Land Department site inspection of 20 April 2026
32 months past its registered completion date
- Completion date (Land Department)
- February 2024
- Finish at recent pace
- February 2028
- Construction started
- January 2016
- Registered with the Land Department
- December 2015
- Developer
- Orion Real Estate Development
- Community
- Business Bay
- Units
- 253
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- ويست باي تاور
- Land Department project number
- 1701
- Land Department site inspections
- 23
Schedule
West Bay Tower was registered to complete in February 2024, 32 months ago, and is still under construction. Over the last year of inspections it has added about 0.8 points a month. Kept at that rate, the site would reach 100% around February 2028.
Site inspections
20 April 2026
83%+4.0 pts
28 January 2026
78%+1.9 pts
11 September 2025
77%+14 pts
11 April 2025
62%+5.1 pts
11 November 2024
57%+9.2 pts
13 February 2024
48%+9.5 pts
1 August 2023
39%+4.6 pts
17 March 2023
34%+3.8 pts
24 November 2022
30%+2.9 pts
20 July 2022
27%+2.1 pts
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in West Bay Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will West Bay Tower be completed?
- The completion date registered with the Dubai Land Department is February 2024. At the pace of its recent inspections the site would reach 100% around February 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of West Bay Tower is built?
- 83%, measured at the Land Department site inspection on 20 April 2026. The Land Department engineers have inspected the site 23 times since October 2016.
- Is West Bay Tower delayed?
- Yes. Its registered completion date of February 2024 has passed and the Land Department still lists it as under construction.
- Who is building West Bay Tower?
- The registered developer is Orion Real Estate Development.
- Which bank holds the escrow account for West Bay Tower?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)