Luxury Family Residence III construction progress

Luxury Family Residence III in Business Bay was registered to complete in June 2025 and is still under construction. At the last site inspection, in May 2026, it was 51% built. The developer is Kappa Acca Real Estate Development.

51%

Built, at the site inspection of 7 May 2026

17 months past its registered completion date

Registered completion date
June 2025
Finish at recent pace
December 2030
Construction started
June 2022
First registered
January 2023
Developer
Kappa Acca Real Estate Development
Community
Business Bay
Units
72
Escrow bank
Al Masraf
Name in Arabic
Iii لوكجري فاميلي ريزيدنس
Project number
2477
Site inspections
7

Schedule

Luxury Family Residence III was registered to complete in June 2025, 17 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around December 2030.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 May 2026

51%+4.8 pts

  • Luxury Family Residence III construction site, inspection photo 1, 7 May 2026
  • Luxury Family Residence III construction site, inspection photo 2, 7 May 2026
  • Luxury Family Residence III construction site, inspection photo 3, 7 May 2026
  • Luxury Family Residence III construction site, inspection photo 4, 7 May 2026

24 November 2025

46%+5.4 pts

  • Luxury Family Residence III construction site, inspection photo 1, 24 November 2025
  • Luxury Family Residence III construction site, inspection photo 2, 24 November 2025
  • Luxury Family Residence III construction site, inspection photo 3, 24 November 2025
  • Luxury Family Residence III construction site, inspection photo 4, 24 November 2025

19 March 2025

40%+4.0 pts

  • Luxury Family Residence III construction site, inspection photo 1, 19 March 2025
  • Luxury Family Residence III construction site, inspection photo 2, 19 March 2025
  • Luxury Family Residence III construction site, inspection photo 3, 19 March 2025
  • Luxury Family Residence III construction site, inspection photo 4, 19 March 2025

2 October 2024

36%+6.2 pts

  • Luxury Family Residence III construction site, inspection photo 1, 2 October 2024
  • Luxury Family Residence III construction site, inspection photo 2, 2 October 2024
  • Luxury Family Residence III construction site, inspection photo 3, 2 October 2024
  • Luxury Family Residence III construction site, inspection photo 4, 2 October 2024

15 February 2024

30%+7.5 pts

  • Luxury Family Residence III construction site, inspection photo 1, 15 February 2024
  • Luxury Family Residence III construction site, inspection photo 2, 15 February 2024
  • Luxury Family Residence III construction site, inspection photo 3, 15 February 2024
  • Luxury Family Residence III construction site, inspection photo 4, 15 February 2024

16 August 2023

23%+19 pts

  • Luxury Family Residence III construction site, inspection photo 1, 16 August 2023
  • Luxury Family Residence III construction site, inspection photo 2, 16 August 2023
  • Luxury Family Residence III construction site, inspection photo 3, 16 August 2023
  • Luxury Family Residence III construction site, inspection photo 4, 16 August 2023

10 October 2022

4.1%

  • Luxury Family Residence III construction site, inspection photo 1, 10 October 2022
  • Luxury Family Residence III construction site, inspection photo 2, 10 October 2022
  • Luxury Family Residence III construction site, inspection photo 3, 10 October 2022
  • Luxury Family Residence III construction site, inspection photo 4, 10 October 2022

All 42 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Kappa Acca Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Luxury Family Residence III?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Luxury Family Residence III handover date?
The registered completion date was June 2025, and the register still lists Luxury Family Residence III as under construction. At the pace of its recent inspections the site would reach 100% around December 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Luxury Family Residence III?
Luxury Family Residence III was 51% built at the site inspection on 7 May 2026. The site has been inspected 7 times since October 2022. The Land Department took 42 site photos at its inspections.
Is Luxury Family Residence III delayed?
Yes. Its registered completion date of June 2025 has passed and the project is still listed as under construction.
Who is building Luxury Family Residence III?
The registered developer is Kappa Acca Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Luxury Family Residence III?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.