Luxury Family Residence III construction progress
Luxury Family Residence III in Business Bay was registered to complete in June 2025 and is still under construction. At the last site inspection, in May 2026, it was 51% built. The developer is Kappa Acca Real Estate Development.
51%
Built, at the site inspection of 7 May 2026
17 months past its registered completion date
- Registered completion date
- June 2025
- Finish at recent pace
- December 2030
- Construction started
- June 2022
- First registered
- January 2023
- Developer
- Kappa Acca Real Estate Development
- Community
- Business Bay
- Units
- 72
- Escrow bank
- Al Masraf
- Name in Arabic
- Iii لوكجري فاميلي ريزيدنس
- Project number
- 2477
- Site inspections
- 7
Schedule
Luxury Family Residence III was registered to complete in June 2025, 17 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around December 2030.
Site inspections
7 May 2026
51%+4.8 pts
24 November 2025
46%+5.4 pts
19 March 2025
40%+4.0 pts
2 October 2024
36%+6.2 pts
15 February 2024
30%+7.5 pts
16 August 2023
23%+19 pts
10 October 2022
4.1%
Context
Business Bay has 43 projects under construction, 37% built on average.
Kappa Acca Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Luxury Family Residence III?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Luxury Family Residence III handover date?
- The registered completion date was June 2025, and the register still lists Luxury Family Residence III as under construction. At the pace of its recent inspections the site would reach 100% around December 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Luxury Family Residence III?
- Luxury Family Residence III was 51% built at the site inspection on 7 May 2026. The site has been inspected 7 times since October 2022. The Land Department took 42 site photos at its inspections.
- Is Luxury Family Residence III delayed?
- Yes. Its registered completion date of June 2025 has passed and the project is still listed as under construction.
- Who is building Luxury Family Residence III?
- The registered developer is Kappa Acca Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Luxury Family Residence III?
- Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Luxury Family ResidenceAlso by Kappa Acca Real Estate Development. 76%, Due December 2023, passed.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)