Aykon City 3 construction progress
The registered completion date for Aykon City 3 in Business Bay is December 2027. At the last site inspection, in November 2026, it was 38% built. The developer is Damac Canal One Property Development.
38%
Built, at the site inspection of 3 November 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- April 2031
- Construction started
- December 2019
- First registered
- December 2019
- Developer
- Damac Canal One Property Development
- Community
- Business Bay
- Units
- 1,300
- Escrow bank
- Emirates NBD
- Name in Arabic
- ايكون سيتي 3
- Project number
- 2200
- Site inspections
- 11
Schedule
Between December 2025 and November 2026 the site added about 1.2 points a month. At that rate it would finish around April 2031, more than three months after its registered date of December 2027.
Site inspections
3 November 2026
38%+6.9 pts
12 April 2026
31%+5.0 pts
25 December 2025
26%+3.0 pts
28 July 2025
23%+5.3 pts
19 March 2025
18%+8.4 pts
14 October 2024
9.7%+3.1 pts
14 December 2023
6.6%+3.5 pts
5 September 2023
3.1%+0.4 pts
16 May 2023
2.7%+1.4 pts
30 December 2022
1.3%+0.3 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Aykon City 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Aykon City 3 handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Aykon City 3?
- Aykon City 3 was 38% built at the site inspection on 3 November 2026. The site has been inspected 11 times since September 2022. The Land Department took 72 site photos at its inspections.
- Is Aykon City 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Aykon City 3?
- The registered developer is Damac Canal One Property Development.
- Which bank holds the escrow account for Aykon City 3?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)