Binghatti Aquarise construction progress
Binghatti Aquarise in Business Bay was registered to complete in October 2026 and is still under construction. At the last site inspection, in October 2026, it was 28% built. The developer is Binghatti Developers.
28%
Built, at the site inspection of 22 October 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- May 2031
- Construction started
- March 2025
- First registered
- April 2025
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 1,592
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بن غاطي أكوا رايز
- Project number
- 3585
- Site inspections
- 3
Schedule
Binghatti Aquarise was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around May 2031.
Site inspections
22 October 2026
28%+7.0 pts
14 May 2026
21%+21 pts
6 March 2025
0%
Context
Business Bay has 43 projects under construction, 37% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Aquarise?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Aquarise handover date?
- The registered completion date was October 2026, and the register still lists Binghatti Aquarise as under construction. At the pace of its recent inspections the site would reach 100% around May 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Aquarise?
- Binghatti Aquarise was 28% built at the site inspection on 22 October 2026. The site has been inspected 3 times since March 2025. The Land Department took 14 site photos at its inspections.
- Is Binghatti Aquarise delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Binghatti Aquarise?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Aquarise?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)