Binghatti Aquarise construction progress
Binghatti Aquarise in Business Bay is 21% built at the Land Department inspection of May 2026. Developer Binghatti Developers. Completion registered for October 2026.
21%
Built, at the Land Department site inspection of 14 May 2026
Running behind its date
- Completion date (Land Department)
- October 2026
- Finish at recent pace
- October 2030
- Construction started
- March 2025
- Registered with the Land Department
- April 2025
- Developer
- Binghatti Developers
- Community
- Business Bay
- Units
- 1,592
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بن غاطي أكوا رايز
- Land Department project number
- 3585
- Land Department site inspections
- 2
Schedule
Between March 2025 and May 2026 the site added about 1.5 points a month. At that rate it would finish around October 2030, more than three months after the October 2026 date registered with the Land Department.
Site inspections
14 May 2026
21%+21 pts
6 March 2025
0%
Context
Business Bay has 43 projects under construction, 35% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Aquarise?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Aquarise be completed?
- The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around October 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Aquarise is built?
- 21%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 2 times since March 2025.
- Is Binghatti Aquarise delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
- Who is building Binghatti Aquarise?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Aquarise?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Burj PacificNearby in Business Bay. 99%, Due January 2023, passed.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.