Canal Heights construction progress

The registered completion date for Canal Heights in Business Bay is December 2026. At the last site inspection, in August 2026, it was 36% built. The developer is Vesta Real Estate Development.

36%

Built, at the site inspection of 17 August 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
February 2030
Construction started
May 2023
First registered
March 2023
Developer
Vesta Real Estate Development
Community
Business Bay
Units
415
Escrow bank
Emirates NBD
Name in Arabic
قنال هايتس
Project number
2602
Site inspections
8

Schedule

Between August 2025 and August 2026 the site added about 1.5 points a month. At that rate it would finish around February 2030, more than three months after its registered date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 August 2026

36%+5.1 pts

  • Canal Heights construction site, inspection photo 1, 17 August 2026
  • Canal Heights construction site, inspection photo 2, 17 August 2026
  • Canal Heights construction site, inspection photo 3, 17 August 2026
  • Canal Heights construction site, inspection photo 4, 17 August 2026

22 April 2026

31%+7.6 pts

  • Canal Heights construction site, inspection photo 1, 22 April 2026
  • Canal Heights construction site, inspection photo 2, 22 April 2026
  • Canal Heights construction site, inspection photo 3, 22 April 2026
  • Canal Heights construction site, inspection photo 4, 22 April 2026

27 December 2025

24%+5.5 pts

  • Canal Heights construction site, inspection photo 1, 27 December 2025
  • Canal Heights construction site, inspection photo 2, 27 December 2025
  • Canal Heights construction site, inspection photo 3, 27 December 2025
  • Canal Heights construction site, inspection photo 4, 27 December 2025

19 August 2025

18%+5.4 pts

  • Canal Heights construction site, inspection photo 1, 19 August 2025
  • Canal Heights construction site, inspection photo 2, 19 August 2025
  • Canal Heights construction site, inspection photo 3, 19 August 2025
  • Canal Heights construction site, inspection photo 4, 19 August 2025

11 April 2025

13%+4.3 pts

  • Canal Heights construction site, inspection photo 1, 11 April 2025
  • Canal Heights construction site, inspection photo 2, 11 April 2025
  • Canal Heights construction site, inspection photo 3, 11 April 2025
  • Canal Heights construction site, inspection photo 4, 11 April 2025

5 July 2024

8.5%+8.4 pts

  • Canal Heights construction site, inspection photo 1, 5 July 2024
  • Canal Heights construction site, inspection photo 2, 5 July 2024

21 September 2023

0.1%+0.1 pts

  • Canal Heights construction site, inspection photo 1, 21 September 2023
  • Canal Heights construction site, inspection photo 2, 21 September 2023
  • Canal Heights construction site, inspection photo 3, 21 September 2023
  • Canal Heights construction site, inspection photo 4, 21 September 2023

1 March 2023

0%

  • Canal Heights construction site, inspection photo 1, 1 March 2023
  • Canal Heights construction site, inspection photo 2, 1 March 2023
  • Canal Heights construction site, inspection photo 3, 1 March 2023

All 47 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Canal Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Canal Heights handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Canal Heights?
Canal Heights was 36% built at the site inspection on 17 August 2026. The site has been inspected 8 times since March 2023. The Land Department took 47 site photos at its inspections.
Is Canal Heights delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Canal Heights?
The registered developer is Vesta Real Estate Development.
Which bank holds the escrow account for Canal Heights?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.