Burj Pacific construction progress
Burj Pacific in Business Bay is 99% built at the Land Department inspection of August 2025. Developer Pacific Ventures Limited. Completion registered for January 2023.
99%
Built, at the Land Department site inspection of 19 August 2025
44 months past its registered completion date
- Completion date (Land Department)
- January 2023
- Finish at recent pace
- July 2026
- Construction started
- January 2012
- Registered with the Land Department
- February 2013
- Developer
- Pacific Ventures Limited
- Community
- Business Bay
- Units
- 145
- Escrow bank
- Mashreq Bank
- Name in Arabic
- برج باسيفك
- Land Department project number
- 266
- Land Department site inspections
- 31
Schedule
Burj Pacific was registered to complete in January 2023, 44 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
19 August 2025
99%+0.7 pts
27 March 2025
98%+0.5 pts
28 September 2024
98%+2.5 pts
22 February 2024
95%+2.6 pts
4 September 2023
92%+0.1 pts
18 July 2023
92%+0.4 pts
15 March 2023
92%+0.3 pts
31 August 2022
92%+0.4 pts
14 March 2022
91%+1.7 pts
22 November 2021
90%+1.4 pts
Context
Business Bay has 43 projects under construction, 35% built on average.
Own a unit in Burj Pacific?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Burj Pacific be completed?
- The completion date registered with the Dubai Land Department is January 2023. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Burj Pacific is built?
- 99%, measured at the Land Department site inspection on 19 August 2025. The Land Department engineers have inspected the site 31 times since July 2013.
- Is Burj Pacific delayed?
- Yes. Its registered completion date of January 2023 has passed and the Land Department still lists it as under construction.
- Who is building Burj Pacific?
- The registered developer is Pacific Ventures Limited.
- Which bank holds the escrow account for Burj Pacific?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 31%, Due December 2027.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)