Burj Pacific construction progress
Burj Pacific in Business Bay was registered to complete in January 2023 and is still under construction. At the last site inspection, in August 2025, it was 99% built. The developer is Pacific Ventures Limited.
99%
Built, at the site inspection of 19 August 2025
46 months past its registered completion date
- Registered completion date
- January 2023
- Finish at recent pace
- July 2026
- Construction started
- January 2012
- First registered
- February 2013
- Developer
- Pacific Ventures Limited
- Community
- Business Bay
- Units
- 145
- Escrow bank
- Mashreq Bank
- Name in Arabic
- برج باسيفك
- Project number
- 266
- Site inspections
- 31
Schedule
Burj Pacific was registered to complete in January 2023, 46 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around July 2026.
Site inspections
19 August 2025
99%+0.7 pts
27 March 2025
98%+0.5 pts
28 September 2024
98%+2.5 pts
22 February 2024
95%+2.6 pts
4 September 2023
92%+0.1 pts
18 July 2023
92%+0.4 pts
15 March 2023
92%+0.3 pts
31 August 2022
92%+0.4 pts
14 March 2022
91%+1.7 pts
22 November 2021
90%+1.4 pts
Context
Business Bay has 43 projects under construction, 37% built on average.
Own a unit in Burj Pacific?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Burj Pacific handover date?
- The registered completion date was January 2023, and the register still lists Burj Pacific as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Burj Pacific?
- Burj Pacific was 99% built at the site inspection on 19 August 2025. The site has been inspected 31 times since July 2013. The Land Department took 277 site photos at its inspections.
- Is Burj Pacific delayed?
- Yes. Its registered completion date of January 2023 has passed and the project is still listed as under construction.
- Who is building Burj Pacific?
- The registered developer is Pacific Ventures Limited.
- Which bank holds the escrow account for Burj Pacific?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 77sNearby in Business Bay. 14%, Due December 2028.
- West Bay TowerNearby in Business Bay. 83%, Due February 2024, passed.
- Aykon City 3Nearby in Business Bay. 38%, Due December 2027.
- Chic TowerNearby in Business Bay. 84%, Due July 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)