Burj Pacific construction progress

Burj Pacific in Business Bay is 99% built at the Land Department inspection of August 2025. Developer Pacific Ventures Limited. Completion registered for January 2023.

99%

Built, at the Land Department site inspection of 19 August 2025

44 months past its registered completion date

Completion date (Land Department)
January 2023
Finish at recent pace
July 2026
Construction started
January 2012
Registered with the Land Department
February 2013
Developer
Pacific Ventures Limited
Community
Business Bay
Units
145
Escrow bank
Mashreq Bank
Name in Arabic
برج باسيفك
Land Department project number
266
Land Department site inspections
31

Schedule

Burj Pacific was registered to complete in January 2023, 44 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around July 2026.

0%25%50%75%100%20132016201920222025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 August 2025

99%+0.7 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 19 August 2025
  • Burj Pacific construction site, Land Department inspection photo 2, 19 August 2025
  • Burj Pacific construction site, Land Department inspection photo 3, 19 August 2025
  • Burj Pacific construction site, Land Department inspection photo 4, 19 August 2025

27 March 2025

98%+0.5 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 27 March 2025
  • Burj Pacific construction site, Land Department inspection photo 2, 27 March 2025
  • Burj Pacific construction site, Land Department inspection photo 3, 27 March 2025
  • Burj Pacific construction site, Land Department inspection photo 4, 27 March 2025

28 September 2024

98%+2.5 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 28 September 2024
  • Burj Pacific construction site, Land Department inspection photo 2, 28 September 2024
  • Burj Pacific construction site, Land Department inspection photo 3, 28 September 2024
  • Burj Pacific construction site, Land Department inspection photo 4, 28 September 2024

22 February 2024

95%+2.6 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 22 February 2024
  • Burj Pacific construction site, Land Department inspection photo 2, 22 February 2024
  • Burj Pacific construction site, Land Department inspection photo 3, 22 February 2024
  • Burj Pacific construction site, Land Department inspection photo 4, 22 February 2024

4 September 2023

92%+0.1 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 4 September 2023
  • Burj Pacific construction site, Land Department inspection photo 2, 4 September 2023
  • Burj Pacific construction site, Land Department inspection photo 3, 4 September 2023
  • Burj Pacific construction site, Land Department inspection photo 4, 4 September 2023

18 July 2023

92%+0.4 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 18 July 2023
  • Burj Pacific construction site, Land Department inspection photo 2, 18 July 2023
  • Burj Pacific construction site, Land Department inspection photo 3, 18 July 2023
  • Burj Pacific construction site, Land Department inspection photo 4, 18 July 2023

15 March 2023

92%+0.3 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 15 March 2023
  • Burj Pacific construction site, Land Department inspection photo 2, 15 March 2023
  • Burj Pacific construction site, Land Department inspection photo 3, 15 March 2023
  • Burj Pacific construction site, Land Department inspection photo 4, 15 March 2023

31 August 2022

92%+0.4 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 31 August 2022
  • Burj Pacific construction site, Land Department inspection photo 2, 31 August 2022
  • Burj Pacific construction site, Land Department inspection photo 3, 31 August 2022
  • Burj Pacific construction site, Land Department inspection photo 4, 31 August 2022

14 March 2022

91%+1.7 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 14 March 2022
  • Burj Pacific construction site, Land Department inspection photo 2, 14 March 2022
  • Burj Pacific construction site, Land Department inspection photo 3, 14 March 2022
  • Burj Pacific construction site, Land Department inspection photo 4, 14 March 2022

22 November 2021

90%+1.4 pts

  • Burj Pacific construction site, Land Department inspection photo 1, 22 November 2021
  • Burj Pacific construction site, Land Department inspection photo 2, 22 November 2021
  • Burj Pacific construction site, Land Department inspection photo 3, 22 November 2021
  • Burj Pacific construction site, Land Department inspection photo 4, 22 November 2021

All 277 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 35% built on average.

Own a unit in Burj Pacific?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Burj Pacific be completed?
The completion date registered with the Dubai Land Department is January 2023. At the pace of its recent inspections the site would reach 100% around July 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Burj Pacific is built?
99%, measured at the Land Department site inspection on 19 August 2025. The Land Department engineers have inspected the site 31 times since July 2013.
Is Burj Pacific delayed?
Yes. Its registered completion date of January 2023 has passed and the Land Department still lists it as under construction.
Who is building Burj Pacific?
The registered developer is Pacific Ventures Limited.
Which bank holds the escrow account for Burj Pacific?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.