Burj Pacific construction progress

Burj Pacific in Business Bay was registered to complete in January 2023 and is still under construction. At the last site inspection, in August 2025, it was 99% built. The developer is Pacific Ventures Limited.

99%

Built, at the site inspection of 19 August 2025

46 months past its registered completion date

Registered completion date
January 2023
Finish at recent pace
July 2026
Construction started
January 2012
First registered
February 2013
Developer
Pacific Ventures Limited
Community
Business Bay
Units
145
Escrow bank
Mashreq Bank
Name in Arabic
برج باسيفك
Project number
266
Site inspections
31

Schedule

Burj Pacific was registered to complete in January 2023, 46 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around July 2026.

0%25%50%75%100%20132016201920222025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 August 2025

99%+0.7 pts

  • Burj Pacific construction site, inspection photo 1, 19 August 2025
  • Burj Pacific construction site, inspection photo 2, 19 August 2025
  • Burj Pacific construction site, inspection photo 3, 19 August 2025
  • Burj Pacific construction site, inspection photo 4, 19 August 2025

27 March 2025

98%+0.5 pts

  • Burj Pacific construction site, inspection photo 1, 27 March 2025
  • Burj Pacific construction site, inspection photo 2, 27 March 2025
  • Burj Pacific construction site, inspection photo 3, 27 March 2025
  • Burj Pacific construction site, inspection photo 4, 27 March 2025

28 September 2024

98%+2.5 pts

  • Burj Pacific construction site, inspection photo 1, 28 September 2024
  • Burj Pacific construction site, inspection photo 2, 28 September 2024
  • Burj Pacific construction site, inspection photo 3, 28 September 2024
  • Burj Pacific construction site, inspection photo 4, 28 September 2024

22 February 2024

95%+2.6 pts

  • Burj Pacific construction site, inspection photo 1, 22 February 2024
  • Burj Pacific construction site, inspection photo 2, 22 February 2024
  • Burj Pacific construction site, inspection photo 3, 22 February 2024
  • Burj Pacific construction site, inspection photo 4, 22 February 2024

4 September 2023

92%+0.1 pts

  • Burj Pacific construction site, inspection photo 1, 4 September 2023
  • Burj Pacific construction site, inspection photo 2, 4 September 2023
  • Burj Pacific construction site, inspection photo 3, 4 September 2023
  • Burj Pacific construction site, inspection photo 4, 4 September 2023

18 July 2023

92%+0.4 pts

  • Burj Pacific construction site, inspection photo 1, 18 July 2023
  • Burj Pacific construction site, inspection photo 2, 18 July 2023
  • Burj Pacific construction site, inspection photo 3, 18 July 2023
  • Burj Pacific construction site, inspection photo 4, 18 July 2023

15 March 2023

92%+0.3 pts

  • Burj Pacific construction site, inspection photo 1, 15 March 2023
  • Burj Pacific construction site, inspection photo 2, 15 March 2023
  • Burj Pacific construction site, inspection photo 3, 15 March 2023
  • Burj Pacific construction site, inspection photo 4, 15 March 2023

31 August 2022

92%+0.4 pts

  • Burj Pacific construction site, inspection photo 1, 31 August 2022
  • Burj Pacific construction site, inspection photo 2, 31 August 2022
  • Burj Pacific construction site, inspection photo 3, 31 August 2022
  • Burj Pacific construction site, inspection photo 4, 31 August 2022

14 March 2022

91%+1.7 pts

  • Burj Pacific construction site, inspection photo 1, 14 March 2022
  • Burj Pacific construction site, inspection photo 2, 14 March 2022
  • Burj Pacific construction site, inspection photo 3, 14 March 2022
  • Burj Pacific construction site, inspection photo 4, 14 March 2022

22 November 2021

90%+1.4 pts

  • Burj Pacific construction site, inspection photo 1, 22 November 2021
  • Burj Pacific construction site, inspection photo 2, 22 November 2021
  • Burj Pacific construction site, inspection photo 3, 22 November 2021
  • Burj Pacific construction site, inspection photo 4, 22 November 2021

All 277 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Burj Pacific?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Burj Pacific handover date?
The registered completion date was January 2023, and the register still lists Burj Pacific as under construction. At the pace of its recent inspections the site would reach 100% around July 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Burj Pacific?
Burj Pacific was 99% built at the site inspection on 19 August 2025. The site has been inspected 31 times since July 2013. The Land Department took 277 site photos at its inspections.
Is Burj Pacific delayed?
Yes. Its registered completion date of January 2023 has passed and the project is still listed as under construction.
Who is building Burj Pacific?
The registered developer is Pacific Ventures Limited.
Which bank holds the escrow account for Burj Pacific?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.