Vela Viento By Omniyat construction progress

The registered completion date for Vela Viento By Omniyat in Business Bay is May 2027. At the last site inspection, in May 2026, it was 22% built. The developer is Royal Creek Real Estate Development.

22%

Built, at the site inspection of 18 May 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
August 2031
Construction started
January 2024
First registered
July 2024
Developer
Royal Creek Real Estate Development
Community
Business Bay
Units
96
Escrow bank
Commercial Bank of Dubai
Name in Arabic
فيلا فينتو من أمنيات
Project number
2885
Site inspections
7

Schedule

Between July 2025 and May 2026 the site added about 1.2 points a month. At that rate it would finish around August 2031, more than three months after its registered date of May 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 May 2026

22%+3.8 pts

  • Vela Viento By Omniyat construction site, inspection photo 1, 18 May 2026
  • Vela Viento By Omniyat construction site, inspection photo 2, 18 May 2026
  • Vela Viento By Omniyat construction site, inspection photo 3, 18 May 2026
  • Vela Viento By Omniyat construction site, inspection photo 4, 18 May 2026

16 February 2026

18%+3.7 pts

  • Vela Viento By Omniyat construction site, inspection photo 1, 16 February 2026
  • Vela Viento By Omniyat construction site, inspection photo 2, 16 February 2026
  • Vela Viento By Omniyat construction site, inspection photo 3, 16 February 2026
  • Vela Viento By Omniyat construction site, inspection photo 4, 16 February 2026

3 November 2025

14%+5.5 pts

  • Vela Viento By Omniyat construction site, inspection photo 1, 3 November 2025
  • Vela Viento By Omniyat construction site, inspection photo 2, 3 November 2025
  • Vela Viento By Omniyat construction site, inspection photo 3, 3 November 2025
  • Vela Viento By Omniyat construction site, inspection photo 4, 3 November 2025

4 July 2025

8.8%+1.6 pts

  • Vela Viento By Omniyat construction site, inspection photo 1, 4 July 2025
  • Vela Viento By Omniyat construction site, inspection photo 2, 4 July 2025
  • Vela Viento By Omniyat construction site, inspection photo 3, 4 July 2025
  • Vela Viento By Omniyat construction site, inspection photo 4, 4 July 2025

9 May 2025

7.3%+0.9 pts

  • Vela Viento By Omniyat construction site, inspection photo 1, 9 May 2025
  • Vela Viento By Omniyat construction site, inspection photo 2, 9 May 2025
  • Vela Viento By Omniyat construction site, inspection photo 3, 9 May 2025
  • Vela Viento By Omniyat construction site, inspection photo 4, 9 May 2025

17 March 2025

6.3%+6.3 pts

  • Vela Viento By Omniyat construction site, inspection photo 1, 17 March 2025
  • Vela Viento By Omniyat construction site, inspection photo 2, 17 March 2025
  • Vela Viento By Omniyat construction site, inspection photo 3, 17 March 2025

27 February 2024

0%

  • Vela Viento By Omniyat construction site, inspection photo 1, 27 February 2024
  • Vela Viento By Omniyat construction site, inspection photo 2, 27 February 2024

All 33 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Vela Viento By Omniyat?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vela Viento By Omniyat handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vela Viento By Omniyat?
Vela Viento By Omniyat was 22% built at the site inspection on 18 May 2026. The site has been inspected 7 times since February 2024. The Land Department took 33 site photos at its inspections.
Is Vela Viento By Omniyat delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Vela Viento By Omniyat?
The registered developer is Royal Creek Real Estate Development.
Which bank holds the escrow account for Vela Viento By Omniyat?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.