Dg1 Living construction progress

The registered completion date for Dg1 Living in Business Bay is April 2027. At the last site inspection, in October 2026, it was 65% built. The developer is Dar Dg Global Property Development.

65%

Built, at the site inspection of 5 October 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
November 2027
Construction started
September 2023
First registered
May 2023
Developer
Dar Dg Global Property Development
Community
Business Bay
Units
249
Escrow bank
Emirates NBD
Name in Arabic
دج 1 ليفينج
Project number
2616
Site inspections
9

Schedule

Between January 2026 and October 2026 the site added about 2.6 points a month. At that rate it would finish around November 2027, more than three months after its registered date of April 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

65%+12 pts

  • Dg1 Living construction site, inspection photo 1, 5 October 2026
  • Dg1 Living construction site, inspection photo 2, 5 October 2026
  • Dg1 Living construction site, inspection photo 3, 5 October 2026
  • Dg1 Living construction site, inspection photo 4, 5 October 2026

9 June 2026

53%+10 pts

  • Dg1 Living construction site, inspection photo 1, 9 June 2026
  • Dg1 Living construction site, inspection photo 2, 9 June 2026
  • Dg1 Living construction site, inspection photo 3, 9 June 2026
  • Dg1 Living construction site, inspection photo 4, 9 June 2026

19 January 2026

43%+20 pts

  • Dg1 Living construction site, inspection photo 1, 19 January 2026
  • Dg1 Living construction site, inspection photo 2, 19 January 2026
  • Dg1 Living construction site, inspection photo 3, 19 January 2026
  • Dg1 Living construction site, inspection photo 4, 19 January 2026

26 August 2025

23%+5.7 pts

  • Dg1 Living construction site, inspection photo 1, 26 August 2025
  • Dg1 Living construction site, inspection photo 2, 26 August 2025
  • Dg1 Living construction site, inspection photo 3, 26 August 2025
  • Dg1 Living construction site, inspection photo 4, 26 August 2025

28 April 2025

18%+9.4 pts

  • Dg1 Living construction site, inspection photo 1, 28 April 2025
  • Dg1 Living construction site, inspection photo 2, 28 April 2025
  • Dg1 Living construction site, inspection photo 3, 28 April 2025
  • Dg1 Living construction site, inspection photo 4, 28 April 2025

16 December 2024

8.1%+5.0 pts

  • Dg1 Living construction site, inspection photo 1, 16 December 2024
  • Dg1 Living construction site, inspection photo 2, 16 December 2024
  • Dg1 Living construction site, inspection photo 3, 16 December 2024
  • Dg1 Living construction site, inspection photo 4, 16 December 2024

3 June 2024

3.2%+1.1 pts

  • Dg1 Living construction site, inspection photo 1, 3 June 2024
  • Dg1 Living construction site, inspection photo 2, 3 June 2024
  • Dg1 Living construction site, inspection photo 3, 3 June 2024
  • Dg1 Living construction site, inspection photo 4, 3 June 2024

1 April 2024

2.1%+2.1 pts

  • Dg1 Living construction site, inspection photo 1, 1 April 2024
  • Dg1 Living construction site, inspection photo 2, 1 April 2024
  • Dg1 Living construction site, inspection photo 3, 1 April 2024
  • Dg1 Living construction site, inspection photo 4, 1 April 2024

16 March 2023

0%

  • Dg1 Living construction site, inspection photo 1, 16 March 2023
  • Dg1 Living construction site, inspection photo 2, 16 March 2023
  • Dg1 Living construction site, inspection photo 3, 16 March 2023
  • Dg1 Living construction site, inspection photo 4, 16 March 2023

All 65 site photos, by inspection date

Context

Business Bay has 43 projects under construction, 37% built on average.

Own a unit in Dg1 Living?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Dg1 Living handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Dg1 Living?
Dg1 Living was 65% built at the site inspection on 5 October 2026. The site has been inspected 9 times since March 2023. The Land Department took 65 site photos at its inspections.
Is Dg1 Living delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Dg1 Living?
The registered developer is Dar Dg Global Property Development.
Which bank holds the escrow account for Dg1 Living?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.