Binghatti Developers projects under construction
Binghatti Developers has 38 projects under construction in Dubai. On average they are 33% built. 14 have passed their registered completion date. The next one due is Mercedes-Benz Places | Binghatti, in December 2026.
- Binghatti HillsDubai Science Park90%No date set
- Binghatti HillsideDubai Science Park80%Due June 2026, passed
- Binghatti HavenDubai Sports City76%Due March 2026, passed
- Binghatti AmberhallJumeirah Village Circle70%Due February 2026, passed
- Bugatti Residences By BinghattiBusiness Bay66%Due December 2025, passed
- Mercedes-Benz Places | BinghattiDownTown Dubai65%Due December 2026
- Binghatti RubyJumeirah Village Circle65%Due February 2026, passed
- Binghatti StarlightDubai Health Care City Phase 263%Due March 2026, passed
- Binghatti HillcrestArjan60%Due December 2026
- Binghatti TwilightJaddaf Waterfront55%Due April 2026, passed
- Binghatti EliteInternational Media Production Zone53%Due June 2026, passed
- Burj Binghatti Jacob & Co. ResidencesBusiness Bay52%Due June 2026, passed
- One By BinghattiBusiness Bay50%Due May 2026, passed
- Binghatti SkybladeDownTown Dubai40%Due November 2027
- Binghatti SkyriseBusiness Bay36%Due December 2026
- Binghatti HillviewsDubai Science Park33%Due April 2026, passed
- Binghatti SkyhallBusiness Bay31%Due August 2026, passed
- Binghatti AquariseBusiness Bay28%Due October 2026, passed
- Binghatti CircleJumeirah Village Circle22%Due May 2027
- Binghatti Flare 01Jumeirah Village Triangle20%Due July 2027
- Binghatti MoonlightJaddaf Waterfront19%Due June 2026, passed
- Project Maybach19%Due June 2027
- Binghatti Cullinan18%Due June 2027
- Binghatti Flare 02Jumeirah Village Triangle18%Due June 2027
- Maybach Ultimate Luxury18%Due August 2027
- Maybach Six17%Due August 2027
- Binghatti Skyflame 115%Due December 2027
- Binghatti TitaniaMajan15%Due February 2027
- Binghatti Skyflame 212%Due December 2027
- Binghatti VintageMajan11%Due March 2027
- Binghatti Etherea7.2%Due December 2027
- Binghatti Luxuria7.0%Due July 2027
- Binghatti Skyterraces7.0%Due October 2027
- Binghatti Spectre0%Due December 2028
- Binghatti Starfall0%Due September 2028
- Binghatti Wraith0%Due December 2027
- The Atelier0%Due April 2029
- Vision Iconic0%Due December 2028
Questions
How many projects is Binghatti Developers building in Dubai?
38 projects are under construction, 33% built on average at the latest site inspections.
Which Binghatti Developers projects finish next?
By registered completion date: Mercedes-Benz Places | Binghatti (December 2026, 65% built), Binghatti Hillcrest (December 2026, 60% built) and Binghatti Skyrise (December 2026, 36% built). RERA asks developers to update these dates as projects move, so check the register before relying on one.
Are any Binghatti Developers projects delayed?
14 of its 38 projects have passed the registered completion date, among them Bugatti Residences By Binghatti, Binghatti Amberhall and Binghatti Ruby. A project counts as late once its registered completion date has passed before it reaches 100%.
Where is Binghatti Developers building?
Its projects are in Business Bay (6), Dubai Science Park (3) and Jumeirah Village Circle (3), and 8 other communities.
Reading these figures
Each percentage is the share of construction recorded at the latest site inspection. The completion date is the one the developer registered, and RERA asks developers to update it when it reviews a project. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.