Binghatti Flare 01 construction progress

The registered completion date for Binghatti Flare 01 in Jumeirah Village Triangle is July 2027. At the last site inspection, in June 2026, it was 20% built. The developer is Binghatti Developers.

20%

Built, at the site inspection of 19 June 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
January 2030
Construction started
July 2025
First registered
August 2025
Units
845
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي فلير 01
Project number
4006
Site inspections
2

Schedule

Between July 2025 and June 2026 the site added about 1.9 points a month. At that rate it would finish around January 2030, more than three months after its registered date of July 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 June 2026

20%+20 pts

  • Binghatti Flare 01 construction site, inspection photo 1, 19 June 2026
  • Binghatti Flare 01 construction site, inspection photo 2, 19 June 2026
  • Binghatti Flare 01 construction site, inspection photo 3, 19 June 2026
  • Binghatti Flare 01 construction site, inspection photo 4, 19 June 2026

29 July 2025

0%

  • Binghatti Flare 01 construction site, inspection photo 1, 29 July 2025
  • Binghatti Flare 01 construction site, inspection photo 2, 29 July 2025

All 8 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Flare 01?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Flare 01 handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Flare 01?
Binghatti Flare 01 was 20% built at the site inspection on 19 June 2026. The site has been inspected 2 times since July 2025. The Land Department took 8 site photos at its inspections.
Is Binghatti Flare 01 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Binghatti Flare 01?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Flare 01?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.