Binghatti Flare 01 construction progress

Binghatti Flare 01 in Jumeirah Village Triangle is 20% built at the Land Department inspection of June 2026. Developer Binghatti Developers. Completion registered for July 2027.

20%

Built, at the Land Department site inspection of 19 June 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
January 2030
Construction started
July 2025
Registered with the Land Department
August 2025
Units
845
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي فلير 01
Land Department project number
4006
Land Department site inspections
2

Schedule

Between July 2025 and June 2026 the site added about 1.9 points a month. At that rate it would finish around January 2030, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 June 2026

20%+20 pts

  • Binghatti Flare 01 construction site, Land Department inspection photo 1, 19 June 2026
  • Binghatti Flare 01 construction site, Land Department inspection photo 2, 19 June 2026
  • Binghatti Flare 01 construction site, Land Department inspection photo 3, 19 June 2026
  • Binghatti Flare 01 construction site, Land Department inspection photo 4, 19 June 2026

29 July 2025

0%

  • Binghatti Flare 01 construction site, Land Department inspection photo 1, 29 July 2025
  • Binghatti Flare 01 construction site, Land Department inspection photo 2, 29 July 2025

All 8 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Binghatti Flare 01 is behind that average.

Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.

Own a unit in Binghatti Flare 01?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Binghatti Flare 01 be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around January 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Flare 01 is built?
20%, measured at the Land Department site inspection on 19 June 2026. The Land Department engineers have inspected the site 2 times since July 2025.
Is Binghatti Flare 01 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Binghatti Flare 01?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Flare 01?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.