Project Maybach construction progress

The registered completion date for Project Maybach is June 2027. At the last site inspection, in November 2026, it was 19% built. The developer is Binghatti Developers.

19%

Built, at the site inspection of 3 November 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
June 2030
Construction started
January 2026
First registered
January 2026
Units
831
Escrow bank
Dubai Islamic Bank
Name in Arabic
بروجكت مايباخ
Project number
4319
Site inspections
2

Schedule

Between December 2025 and November 2026 the site added about 1.9 points a month. At that rate it would finish around June 2030, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

19%+19 pts

  • Project Maybach construction site, inspection photo 1, 3 November 2026
  • Project Maybach construction site, inspection photo 2, 3 November 2026
  • Project Maybach construction site, inspection photo 3, 3 November 2026
  • Project Maybach construction site, inspection photo 4, 3 November 2026

29 December 2025

0%

  • Project Maybach construction site, inspection photo 1, 29 December 2025
  • Project Maybach construction site, inspection photo 2, 29 December 2025

All 10 site photos, by inspection date

Context

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Project Maybach?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Project Maybach handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Project Maybach?
Project Maybach was 19% built at the site inspection on 3 November 2026. The site has been inspected 2 times since December 2025. The Land Department took 10 site photos at its inspections.
Is Project Maybach delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Project Maybach?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Project Maybach?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.