Project Maybach construction progress
The registered completion date for Project Maybach is June 2027. At the last site inspection, in November 2026, it was 19% built. The developer is Binghatti Developers.
19%
Built, at the site inspection of 3 November 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- June 2030
- Construction started
- January 2026
- First registered
- January 2026
- Developer
- Binghatti Developers
- Units
- 831
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بروجكت مايباخ
- Project number
- 4319
- Site inspections
- 2
Schedule
Between December 2025 and November 2026 the site added about 1.9 points a month. At that rate it would finish around June 2030, more than three months after its registered date of June 2027.
Site inspections
3 November 2026
19%+19 pts
29 December 2025
0%
Context
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Project Maybach?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Project Maybach handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Project Maybach?
- Project Maybach was 19% built at the site inspection on 3 November 2026. The site has been inspected 2 times since December 2025. The Land Department took 10 site photos at its inspections.
- Is Project Maybach delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Project Maybach?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Project Maybach?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.