Skip to content

Binghatti Luxuria construction progress

The registered completion date for Binghatti Luxuria is July 2027. At the last site inspection, in September 2026, it was 7.0% built. The developer is Binghatti Developers.

7.0%

Built, at the site inspection of 17 September 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
June 2036
Construction started
January 2026
First registered
January 2026
Units
469
Escrow bank
Mashreq Bank
Name in Arabic
بن غاطي لكزوريا
Project number
4299
Site inspections
2

Schedule

Between December 2025 and September 2026 the site added about 0.8 points a month. At that rate it would finish around June 2036, more than three months after its registered date of July 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

7.0%+7.0 pts

  • Binghatti Luxuria construction site, inspection photo 1, 17 September 2026
  • Binghatti Luxuria construction site, inspection photo 2, 17 September 2026
  • Binghatti Luxuria construction site, inspection photo 3, 17 September 2026

22 December 2025

0%

  • Binghatti Luxuria construction site, inspection photo 1, 22 December 2025
  • Binghatti Luxuria construction site, inspection photo 2, 22 December 2025

All 5 site photos, by inspection date

Context

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Luxuria?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Luxuria handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Luxuria?
Binghatti Luxuria was 7.0% built at the site inspection on 17 September 2026. The site has been inspected 2 times since December 2025. The Land Department took 5 site photos at its inspections.
Is Binghatti Luxuria delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Binghatti Luxuria?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Luxuria?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.