Binghatti Luxuria construction progress
Binghatti Luxuria is 7.0% built at the Land Department inspection of September 2026. Developer Binghatti Developers. Completion registered for July 2027.
7.0%
Built, at the Land Department site inspection of 17 September 2026
Running behind its date
- Completion date (Land Department)
- July 2027
- Finish at recent pace
- June 2036
- Construction started
- January 2026
- Registered with the Land Department
- January 2026
- Developer
- Binghatti Developers
- Units
- 469
- Escrow bank
- Mashreq Bank
- Name in Arabic
- بن غاطي لكزوريا
- Land Department project number
- 4299
- Land Department site inspections
- 2
Schedule
Between December 2025 and September 2026 the site added about 0.8 points a month. At that rate it would finish around June 2036, more than three months after the July 2027 date registered with the Land Department.
Site inspections
17 September 2026
7.0%+7.0 pts
22 December 2025
0%
Context
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Luxuria?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Luxuria be completed?
- The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around June 2036. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Luxuria is built?
- 7.0%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 2 times since December 2025.
- Is Binghatti Luxuria delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
- Who is building Binghatti Luxuria?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Luxuria?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)