Binghatti Vintage construction progress

The registered completion date for Binghatti Vintage in Majan is March 2027. At the last site inspection, in October 2026, it was 11% built. The developer is Binghatti Developers.

11%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
January 2036
Construction started
October 2025
First registered
December 2025
Community
Majan
Units
1,572
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي فينتيج
Project number
4102
Site inspections
2

Schedule

Between September 2025 and October 2026 the site added about 0.8 points a month. At that rate it would finish around January 2036, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

11%+11 pts

  • Binghatti Vintage construction site, inspection photo 1, 28 October 2026
  • Binghatti Vintage construction site, inspection photo 2, 28 October 2026
  • Binghatti Vintage construction site, inspection photo 3, 28 October 2026
  • Binghatti Vintage construction site, inspection photo 4, 28 October 2026

23 September 2025

0%

  • Binghatti Vintage construction site, inspection photo 1, 23 September 2025
  • Binghatti Vintage construction site, inspection photo 2, 23 September 2025

All 8 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Vintage?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Vintage handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Vintage?
Binghatti Vintage was 11% built at the site inspection on 28 October 2026. The site has been inspected 2 times since September 2025. The Land Department took 8 site photos at its inspections.
Is Binghatti Vintage delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Binghatti Vintage?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Vintage?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.