Binghatti Vintage construction progress
The registered completion date for Binghatti Vintage in Majan is March 2027. At the last site inspection, in October 2026, it was 11% built. The developer is Binghatti Developers.
11%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- January 2036
- Construction started
- October 2025
- First registered
- December 2025
- Developer
- Binghatti Developers
- Community
- Majan
- Units
- 1,572
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي فينتيج
- Project number
- 4102
- Site inspections
- 2
Schedule
Between September 2025 and October 2026 the site added about 0.8 points a month. At that rate it would finish around January 2036, more than three months after its registered date of March 2027.
Site inspections
28 October 2026
11%+11 pts
23 September 2025
0%
Context
Majan has 25 projects under construction, 28% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Vintage?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Vintage handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Vintage?
- Binghatti Vintage was 11% built at the site inspection on 28 October 2026. The site has been inspected 2 times since September 2025. The Land Department took 8 site photos at its inspections.
- Is Binghatti Vintage delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Binghatti Vintage?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Vintage?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)


