Binghatti Hillcrest construction progress
Binghatti Hillcrest in Arjan is 60% built at the Land Department inspection of September 2026. Developer Binghatti Developers. Completion registered for December 2026.
60%
Built, at the Land Department site inspection of 17 September 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- June 2027
- Construction started
- October 2025
- Registered with the Land Department
- December 2025
- Developer
- Binghatti Developers
- Community
- Arjan
- Units
- 396
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- بن غاطي هيل كريست
- Land Department project number
- 4105
- Land Department site inspections
- 3
Schedule
Between September 2025 and September 2026 the site added about 4.3 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
17 September 2026
60%+9.8 pts
31 July 2026
50%+41 pts
24 September 2025
9.3%
Context
Arjan has 23 projects under construction, 46% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Hillcrest?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Hillcrest be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Hillcrest is built?
- 60%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 3 times since September 2025.
- Is Binghatti Hillcrest delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Binghatti Hillcrest?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Hillcrest?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Aryene GreensNearby in Arjan. 80%, Due November 2022, passed.
- Vincitore VolareNearby in Arjan. 63%, Due June 2025, passed.
- Samana Mykonos SignatureNearby in Arjan. 80%, Due April 2026, passed.
- Samana SkyrosNearby in Arjan. 71%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.