Binghatti Hillcrest construction progress

The registered completion date for Binghatti Hillcrest in Arjan is December 2026. At the last site inspection, in September 2026, it was 60% built. The developer is Binghatti Developers.

60%

Built, at the site inspection of 17 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
June 2027
Construction started
October 2025
First registered
December 2025
Community
Arjan
Units
396
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي هيل كريست
Project number
4105
Site inspections
3

Schedule

Between September 2025 and September 2026 the site added about 4.3 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 September 2026

60%+9.8 pts

  • Binghatti Hillcrest construction site, inspection photo 1, 17 September 2026
  • Binghatti Hillcrest construction site, inspection photo 2, 17 September 2026
  • Binghatti Hillcrest construction site, inspection photo 3, 17 September 2026
  • Binghatti Hillcrest construction site, inspection photo 4, 17 September 2026

31 July 2026

50%+41 pts

  • Binghatti Hillcrest construction site, inspection photo 1, 31 July 2026
  • Binghatti Hillcrest construction site, inspection photo 2, 31 July 2026
  • Binghatti Hillcrest construction site, inspection photo 3, 31 July 2026
  • Binghatti Hillcrest construction site, inspection photo 4, 31 July 2026

24 September 2025

9.3%

  • Binghatti Hillcrest construction site, inspection photo 1, 24 September 2025
  • Binghatti Hillcrest construction site, inspection photo 2, 24 September 2025
  • Binghatti Hillcrest construction site, inspection photo 3, 24 September 2025
  • Binghatti Hillcrest construction site, inspection photo 4, 24 September 2025

All 33 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Hillcrest?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Hillcrest handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Hillcrest?
Binghatti Hillcrest was 60% built at the site inspection on 17 September 2026. The site has been inspected 3 times since September 2025. The Land Department took 33 site photos at its inspections.
Is Binghatti Hillcrest delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Binghatti Hillcrest?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Hillcrest?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.