Binghatti Skyblade construction progress

The registered completion date for Binghatti Skyblade in DownTown Dubai is November 2027. At the last site inspection, in November 2026, it was 40% built. The developer is Binghatti Developers.

40%

Built, at the site inspection of 17 November 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
May 2028
Construction started
February 2025
First registered
August 2025
Units
596
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي سكاي بليد
Project number
3725
Site inspections
3

Schedule

Between April 2026 and November 2026 the site added about 3.3 points a month. At that rate it would finish around May 2028, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2026

40%+23 pts

  • Binghatti Skyblade construction site, inspection photo 1, 17 November 2026
  • Binghatti Skyblade construction site, inspection photo 2, 17 November 2026
  • Binghatti Skyblade construction site, inspection photo 3, 17 November 2026
  • Binghatti Skyblade construction site, inspection photo 4, 17 November 2026

21 April 2026

17%+11 pts

  • Binghatti Skyblade construction site, inspection photo 1, 21 April 2026
  • Binghatti Skyblade construction site, inspection photo 2, 21 April 2026
  • Binghatti Skyblade construction site, inspection photo 3, 21 April 2026
  • Binghatti Skyblade construction site, inspection photo 4, 21 April 2026

20 August 2025

6.0%

  • Binghatti Skyblade construction site, inspection photo 1, 20 August 2025
  • Binghatti Skyblade construction site, inspection photo 2, 20 August 2025
  • Binghatti Skyblade construction site, inspection photo 3, 20 August 2025

All 25 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Binghatti Developers has 39 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Skyblade?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Skyblade handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Skyblade?
Binghatti Skyblade was 40% built at the site inspection on 17 November 2026. The site has been inspected 3 times since August 2025. The Land Department took 25 site photos at its inspections.
Is Binghatti Skyblade delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Binghatti Skyblade?
The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Skyblade?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.