Binghatti Skyblade construction progress
The registered completion date for Binghatti Skyblade in DownTown Dubai is November 2027. At the last site inspection, in November 2026, it was 40% built. The developer is Binghatti Developers.
40%
Built, at the site inspection of 17 November 2026
Running behind its date
- Registered completion date
- November 2027
- Finish at recent pace
- May 2028
- Construction started
- February 2025
- First registered
- August 2025
- Developer
- Binghatti Developers
- Community
- DownTown Dubai
- Units
- 596
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي سكاي بليد
- Project number
- 3725
- Site inspections
- 3
Schedule
Between April 2026 and November 2026 the site added about 3.3 points a month. At that rate it would finish around May 2028, more than three months after its registered date of November 2027.
Site inspections
17 November 2026
40%+23 pts
21 April 2026
17%+11 pts
20 August 2025
6.0%
Context
DownTown Dubai has 13 projects under construction, 35% built on average.
Binghatti Developers has 39 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Skyblade?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Skyblade handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Skyblade?
- Binghatti Skyblade was 40% built at the site inspection on 17 November 2026. The site has been inspected 3 times since August 2025. The Land Department took 25 site photos at its inspections.
- Is Binghatti Skyblade delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Binghatti Skyblade?
- The registered developer is Binghatti Developers. It has 38 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Skyblade?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- The St. Regis Residences, Downtown DubaiNearby in DownTown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in DownTown Dubai. 72%, Due September 2026, passed.
- Baccarat Hotel And Residences, DubaiNearby in DownTown Dubai. 21%, Due December 2026.
- Rove Home Residences By IrthNearby in DownTown Dubai. 63%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.