Binghatti Elite construction progress
Binghatti Elite in International Media Production Zone is 53% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for June 2026.
53%
Built, at the Land Department site inspection of 20 April 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- March 2027
- Construction started
- November 2024
- Registered with the Land Department
- November 2024
- Developer
- Binghatti Developers
- Community
- International Media Production Zone
- Units
- 1,745
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- بن غاطي إيليت
- Land Department project number
- 3341
- Land Department site inspections
- 3
Schedule
Binghatti Elite was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around March 2027.
Site inspections
20 April 2026
53%+25 pts
3 November 2025
28%+28 pts
17 October 2024
0%
Context
International Media Production Zone has 15 projects under construction, 22% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Elite?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Elite be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Elite is built?
- 53%, measured at the Land Department site inspection on 20 April 2026. The Land Department engineers have inspected the site 3 times since October 2024.
- Is Binghatti Elite delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Binghatti Elite?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Elite?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Samana PortofinoNearby in International Media Production Zone. 60%.
- Samana ResortsNearby in International Media Production Zone. 5.8%.
- Samana Lake ViewsNearby in International Media Production Zone. 23%.
- Samana Lake Views 2Nearby in International Media Production Zone. 8.9%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)