Binghatti Elite construction progress

Binghatti Elite in International Media Production Zone is 53% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for June 2026.

53%

Built, at the Land Department site inspection of 20 April 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
March 2027
Construction started
November 2024
Registered with the Land Department
November 2024
Units
1,745
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
بن غاطي إيليت
Land Department project number
3341
Land Department site inspections
3

Schedule

Binghatti Elite was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 April 2026

53%+25 pts

  • Binghatti Elite construction site, Land Department inspection photo 1, 20 April 2026
  • Binghatti Elite construction site, Land Department inspection photo 2, 20 April 2026
  • Binghatti Elite construction site, Land Department inspection photo 3, 20 April 2026
  • Binghatti Elite construction site, Land Department inspection photo 4, 20 April 2026

3 November 2025

28%+28 pts

  • Binghatti Elite construction site, Land Department inspection photo 1, 3 November 2025
  • Binghatti Elite construction site, Land Department inspection photo 2, 3 November 2025
  • Binghatti Elite construction site, Land Department inspection photo 3, 3 November 2025
  • Binghatti Elite construction site, Land Department inspection photo 4, 3 November 2025

17 October 2024

0%

  • Binghatti Elite construction site, Land Department inspection photo 1, 17 October 2024
  • Binghatti Elite construction site, Land Department inspection photo 2, 17 October 2024

All 15 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 22% built on average.

Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.

Own a unit in Binghatti Elite?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Binghatti Elite be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Elite is built?
53%, measured at the Land Department site inspection on 20 April 2026. The Land Department engineers have inspected the site 3 times since October 2024.
Is Binghatti Elite delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Binghatti Elite?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Elite?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.