Binghatti Elite construction progress

Binghatti Elite in International Media Production Zone was registered to complete in June 2026 and is still under construction. At the last site inspection, in April 2026, it was 53% built. The developer is Binghatti Developers.

53%

Built, at the site inspection of 20 April 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
March 2027
Construction started
November 2024
First registered
November 2024
Units
1,745
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
بن غاطي إيليت
Project number
3341
Site inspections
3

Schedule

Binghatti Elite was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 April 2026

53%+25 pts

  • Binghatti Elite construction site, inspection photo 1, 20 April 2026
  • Binghatti Elite construction site, inspection photo 2, 20 April 2026
  • Binghatti Elite construction site, inspection photo 3, 20 April 2026
  • Binghatti Elite construction site, inspection photo 4, 20 April 2026

3 November 2025

28%+28 pts

  • Binghatti Elite construction site, inspection photo 1, 3 November 2025
  • Binghatti Elite construction site, inspection photo 2, 3 November 2025
  • Binghatti Elite construction site, inspection photo 3, 3 November 2025
  • Binghatti Elite construction site, inspection photo 4, 3 November 2025

17 October 2024

0%

  • Binghatti Elite construction site, inspection photo 1, 17 October 2024
  • Binghatti Elite construction site, inspection photo 2, 17 October 2024

All 15 site photos, by inspection date

Context

International Media Production Zone has 15 projects under construction, 23% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Elite?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Elite handover date?
The registered completion date was June 2026, and the register still lists Binghatti Elite as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Elite?
Binghatti Elite was 53% built at the site inspection on 20 April 2026. The site has been inspected 3 times since October 2024. The Land Department took 15 site photos at its inspections.
Is Binghatti Elite delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Binghatti Elite?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Elite?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.