Binghatti Ruby in Jumeirah Village Circle is 46% built at the Land Department inspection of July 2026. Developer Binghatti Developers. Completion registered for February 2026.

46%

Built, at the Land Department site inspection of 23 July 2026

7 months past its registered completion date

Completion date (Land Department)
February 2026
Finish at recent pace
April 2027
Construction started
January 2025
Registered with the Land Department
April 2025
Units
628
Escrow bank
The National Bank of Fujairah
Name in Arabic
بن غاطي روبي
Land Department project number
3533
Land Department site inspections
3

Schedule

Binghatti Ruby was registered to complete in February 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 6.0 points a month. Kept at that rate, the site would reach 100% around April 2027.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

46%+26 pts

  • Binghatti Ruby construction site, Land Department inspection photo 1, 23 July 2026
  • Binghatti Ruby construction site, Land Department inspection photo 2, 23 July 2026
  • Binghatti Ruby construction site, Land Department inspection photo 3, 23 July 2026
  • Binghatti Ruby construction site, Land Department inspection photo 4, 23 July 2026

10 March 2026

20%+20 pts

  • Binghatti Ruby construction site, Land Department inspection photo 1, 10 March 2026
  • Binghatti Ruby construction site, Land Department inspection photo 2, 10 March 2026
  • Binghatti Ruby construction site, Land Department inspection photo 3, 10 March 2026
  • Binghatti Ruby construction site, Land Department inspection photo 4, 10 March 2026

6 February 2025

0%

  • Binghatti Ruby construction site, Land Department inspection photo 1, 6 February 2025
  • Binghatti Ruby construction site, Land Department inspection photo 2, 6 February 2025

All 27 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. Binghatti Ruby is ahead of that average.

Binghatti Developers has 36 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Binghatti Ruby?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Binghatti Ruby be completed?
The completion date registered with the Dubai Land Department is February 2026. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Ruby is built?
46%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 3 times since February 2025.
Is Binghatti Ruby delayed?
Yes. Its registered completion date of February 2026 has passed and the Land Department still lists it as under construction.
Who is building Binghatti Ruby?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Ruby?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.