Binghatti Ruby construction progress
Binghatti Ruby in Jumeirah Village Circle was registered to complete in February 2026 and is still under construction. At the last site inspection, in October 2026, it was 65% built. The developer is Binghatti Developers.
65%
Built, at the site inspection of 26 October 2026
9 months past its registered completion date
- Registered completion date
- February 2026
- Finish at recent pace
- April 2027
- Construction started
- January 2025
- First registered
- April 2025
- Developer
- Binghatti Developers
- Community
- Jumeirah Village Circle
- Units
- 628
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- بن غاطي روبي
- Project number
- 3533
- Site inspections
- 4
Schedule
Binghatti Ruby was registered to complete in February 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 6.0 points a month. Kept at that rate, the site would reach 100% around April 2027.
Site inspections
26 October 2026
65%+19 pts
23 July 2026
46%+26 pts
10 March 2026
20%+20 pts
6 February 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Ruby?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Ruby handover date?
- The registered completion date was February 2026, and the register still lists Binghatti Ruby as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Ruby?
- Binghatti Ruby was 65% built at the site inspection on 26 October 2026. The site has been inspected 4 times since February 2025. The Land Department took 40 site photos at its inspections.
- Is Binghatti Ruby delayed?
- Yes. Its registered completion date of February 2026 has passed and the project is still listed as under construction.
- Who is building Binghatti Ruby?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Ruby?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)