Binghatti Haven construction progress

Binghatti Haven in Dubai Sports City is 76% built at the Land Department inspection of May 2026. Developer Binghatti Developers. Completion registered for March 2026.

76%

Built, at the Land Department site inspection of 7 May 2026

6 months past its registered completion date

Completion date (Land Department)
March 2026
Finish at recent pace
November 2026
Construction started
December 2024
Registered with the Land Department
March 2025
Units
501
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
بن غاطي هايفن
Land Department project number
3442
Land Department site inspections
3

Schedule

Binghatti Haven was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.1 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 May 2026

76%+1.9 pts

  • Binghatti Haven construction site, Land Department inspection photo 1, 7 May 2026
  • Binghatti Haven construction site, Land Department inspection photo 2, 7 May 2026
  • Binghatti Haven construction site, Land Department inspection photo 3, 7 May 2026
  • Binghatti Haven construction site, Land Department inspection photo 4, 7 May 2026

20 April 2026

74%+65 pts

  • Binghatti Haven construction site, Land Department inspection photo 1, 20 April 2026
  • Binghatti Haven construction site, Land Department inspection photo 2, 20 April 2026
  • Binghatti Haven construction site, Land Department inspection photo 3, 20 April 2026
  • Binghatti Haven construction site, Land Department inspection photo 4, 20 April 2026

24 December 2024

9.6%

  • Binghatti Haven construction site, Land Department inspection photo 1, 24 December 2024
  • Binghatti Haven construction site, Land Department inspection photo 2, 24 December 2024
  • Binghatti Haven construction site, Land Department inspection photo 3, 24 December 2024
  • Binghatti Haven construction site, Land Department inspection photo 4, 24 December 2024

All 16 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 44% built on average.

Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.

Own a unit in Binghatti Haven?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Binghatti Haven be completed?
The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Haven is built?
76%, measured at the Land Department site inspection on 7 May 2026. The Land Department engineers have inspected the site 3 times since December 2024.
Is Binghatti Haven delayed?
Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
Who is building Binghatti Haven?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Haven?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.