Binghatti Haven construction progress
Binghatti Haven in Dubai Sports City is 76% built at the Land Department inspection of May 2026. Developer Binghatti Developers. Completion registered for March 2026.
76%
Built, at the Land Department site inspection of 7 May 2026
6 months past its registered completion date
- Completion date (Land Department)
- March 2026
- Finish at recent pace
- November 2026
- Construction started
- December 2024
- Registered with the Land Department
- March 2025
- Developer
- Binghatti Developers
- Community
- Dubai Sports City
- Units
- 501
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- بن غاطي هايفن
- Land Department project number
- 3442
- Land Department site inspections
- 3
Schedule
Binghatti Haven was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 4.1 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
7 May 2026
76%+1.9 pts
20 April 2026
74%+65 pts
24 December 2024
9.6%
Context
Dubai Sports City has 21 projects under construction, 44% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Haven?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Haven be completed?
- The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Haven is built?
- 76%, measured at the Land Department site inspection on 7 May 2026. The Land Department engineers have inspected the site 3 times since December 2024.
- Is Binghatti Haven delayed?
- Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
- Who is building Binghatti Haven?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Haven?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.