Binghatti Starlight construction progress
Binghatti Starlight in Dubai Health Care City Phase 2 is 63% built at the Land Department inspection of May 2026. Developer Binghatti Developers. Completion registered for March 2026.
63%
Built, at the Land Department site inspection of 14 May 2026
6 months past its registered completion date
- Completion date (Land Department)
- March 2026
- Finish at recent pace
- December 2026
- Construction started
- July 2024
- Registered with the Land Department
- November 2024
- Developer
- Binghatti Developers
- Community
- Dubai Health Care City Phase 2
- Units
- 511
- Escrow bank
- Emirates NBD
- Name in Arabic
- بن غاطي ستارلايت
- Land Department project number
- 3195
- Land Department site inspections
- 3
Schedule
Binghatti Starlight was registered to complete in March 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 5.5 points a month. Kept at that rate, the site would reach 100% around December 2026.
Site inspections
14 May 2026
63%+34 pts
6 November 2025
29%+29 pts
5 November 2024
0%
Context
Dubai Health Care City Phase 2 has 3 projects under construction, 51% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Starlight?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Starlight be completed?
- The completion date registered with the Dubai Land Department is March 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Starlight is built?
- 63%, measured at the Land Department site inspection on 14 May 2026. The Land Department engineers have inspected the site 3 times since November 2024.
- Is Binghatti Starlight delayed?
- Yes. Its registered completion date of March 2026 has passed and the Land Department still lists it as under construction.
- Who is building Binghatti Starlight?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Starlight?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Keturah ResortNearby in Dubai Health Care City Phase 2. 15%, Due February 2026, passed.
- Adeba AziziNearby in Dubai Health Care City Phase 2. 75%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.









.jpeg&w=3840&q=75)