Binghatti Starlight construction progress

Binghatti Starlight in Dubai Health Care City Phase 2 was registered to complete in March 2026 and is still under construction. At the last site inspection, in May 2026, it was 63% built. The developer is Binghatti Developers.

63%

Built, at the site inspection of 14 May 2026

8 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
December 2026
Construction started
July 2024
First registered
November 2024
Units
511
Escrow bank
Emirates NBD
Name in Arabic
بن غاطي ستارلايت
Project number
3195
Site inspections
3

Schedule

Binghatti Starlight was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 5.5 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 May 2026

63%+34 pts

  • Binghatti Starlight construction site, inspection photo 1, 14 May 2026
  • Binghatti Starlight construction site, inspection photo 2, 14 May 2026
  • Binghatti Starlight construction site, inspection photo 3, 14 May 2026
  • Binghatti Starlight construction site, inspection photo 4, 14 May 2026

6 November 2025

29%+29 pts

  • Binghatti Starlight construction site, inspection photo 1, 6 November 2025
  • Binghatti Starlight construction site, inspection photo 2, 6 November 2025
  • Binghatti Starlight construction site, inspection photo 3, 6 November 2025
  • Binghatti Starlight construction site, inspection photo 4, 6 November 2025

5 November 2024

0%

  • Binghatti Starlight construction site, inspection photo 1, 5 November 2024
  • Binghatti Starlight construction site, inspection photo 2, 5 November 2024

All 34 site photos, by inspection date

Context

Dubai Health Care City Phase 2 has 3 projects under construction, 51% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Starlight?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Starlight handover date?
The registered completion date was March 2026, and the register still lists Binghatti Starlight as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Starlight?
Binghatti Starlight was 63% built at the site inspection on 14 May 2026. The site has been inspected 3 times since November 2024. The Land Department took 34 site photos at its inspections.
Is Binghatti Starlight delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building Binghatti Starlight?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Starlight?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.