Binghatti Hills construction progress

No completion date is registered for Binghatti Hills in Dubai Science Park yet. At the last site inspection, in July 2026, it was 90% built. The developer is Binghatti Developers.

90%

Built, at the site inspection of 24 July 2026

Finish at recent pace
October 2026
Construction started
April 2024
First registered
April 2024
Units
1,701
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي هيلز
Project number
3053
Site inspections
3

Schedule

Since January 2025 Binghatti Hills has added about 3.5 points a month. At that rate the site reaches 100% around October 2026. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

24 July 2026

90%+65 pts

  • Binghatti Hills construction site, inspection photo 1, 24 July 2026
  • Binghatti Hills construction site, inspection photo 2, 24 July 2026
  • Binghatti Hills construction site, inspection photo 3, 24 July 2026
  • Binghatti Hills construction site, inspection photo 4, 24 July 2026

10 January 2025

25%+25 pts

  • Binghatti Hills construction site, inspection photo 1, 10 January 2025
  • Binghatti Hills construction site, inspection photo 2, 10 January 2025
  • Binghatti Hills construction site, inspection photo 3, 10 January 2025
  • Binghatti Hills construction site, inspection photo 4, 10 January 2025

22 April 2024

0%

  • Binghatti Hills construction site, inspection photo 1, 22 April 2024
  • Binghatti Hills construction site, inspection photo 2, 22 April 2024
  • Binghatti Hills construction site, inspection photo 3, 22 April 2024
  • Binghatti Hills construction site, inspection photo 4, 22 April 2024

All 28 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 43% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Hills?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Hills handover date?
No completion date is on record for Binghatti Hills yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Binghatti Hills?
Binghatti Hills was 90% built at the site inspection on 24 July 2026. The site has been inspected 3 times since April 2024. The Land Department took 28 site photos at its inspections.
Who is building Binghatti Hills?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Hills?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.