Maybach Six construction progress

The registered completion date for Maybach Six is August 2027. At the last site inspection, in November 2026, it was 17% built. The developer is Binghatti Developers.

17%

Built, at the site inspection of 3 November 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
November 2030
Construction started
January 2026
First registered
January 2026
Units
1,878
Escrow bank
Dubai Islamic Bank
Name in Arabic
مايباخ 6
Project number
4321
Site inspections
2

Schedule

Between December 2025 and November 2026 the site added about 1.7 points a month. At that rate it would finish around November 2030, more than three months after its registered date of August 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

17%+17 pts

  • Maybach Six construction site, inspection photo 1, 3 November 2026
  • Maybach Six construction site, inspection photo 2, 3 November 2026
  • Maybach Six construction site, inspection photo 3, 3 November 2026
  • Maybach Six construction site, inspection photo 4, 3 November 2026

29 December 2025

0%

  • Maybach Six construction site, inspection photo 1, 29 December 2025
  • Maybach Six construction site, inspection photo 2, 29 December 2025

All 11 site photos, by inspection date

Context

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Maybach Six?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Maybach Six handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Maybach Six?
Maybach Six was 17% built at the site inspection on 3 November 2026. The site has been inspected 2 times since December 2025. The Land Department took 11 site photos at its inspections.
Is Maybach Six delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Maybach Six?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Maybach Six?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.