Binghatti Hillside construction progress
Binghatti Hillside in Dubai Science Park is 80% built at the Land Department inspection of September 2026. Developer Binghatti Developers. Completion registered for June 2026.
80%
Built, at the Land Department site inspection of 17 September 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- May 2027
- Construction started
- January 2025
- Registered with the Land Department
- January 2025
- Developer
- Binghatti Developers
- Community
- Dubai Science Park
- Units
- 411
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي هيل سايد
- Land Department project number
- 3481
- Land Department site inspections
- 3
Schedule
Binghatti Hillside was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around May 2027.
Site inspections
17 September 2026
80%+10.0 pts
19 May 2026
70%+70 pts
10 January 2025
0%
Context
Dubai Science Park has 10 projects under construction, 40% built on average. Binghatti Hillside is ahead of that average.
Binghatti Developers has 36 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Binghatti Hillside?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Binghatti Hillside be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Hillside is built?
- 80%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is Binghatti Hillside delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Binghatti Hillside?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Hillside?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 6.9%.
- Vincitore Aqua FloraNearby in Dubai Science Park. 1.3%, Due June 2028.
- Empire LivingsNearby in Dubai Science Park. 13%, Due November 2027.
- Saas HillsNearby in Dubai Science Park. 13%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.