Binghatti Flare 02 construction progress
Binghatti Flare 02 in Jumeirah Village Triangle is 18% built at the Land Department inspection of June 2026. Developer Binghatti Developers. Completion registered for June 2027.
18%
Built, at the Land Department site inspection of 19 June 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- July 2030
- Construction started
- July 2025
- Registered with the Land Department
- September 2025
- Developer
- Binghatti Developers
- Community
- Jumeirah Village Triangle
- Units
- 613
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي فلير 02
- Land Department project number
- 4008
- Land Department site inspections
- 2
Schedule
Between July 2025 and June 2026 the site added about 1.7 points a month. At that rate it would finish around July 2030, more than three months after the June 2027 date registered with the Land Department.
Site inspections
19 June 2026
18%+18 pts
29 July 2025
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Flare 02?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Binghatti Flare 02 be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around July 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Flare 02 is built?
- 18%, measured at the Land Department site inspection on 19 June 2026. The Land Department engineers have inspected the site 2 times since July 2025.
- Is Binghatti Flare 02 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Binghatti Flare 02?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Flare 02?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Altai TowerNearby in Jumeirah Village Triangle. 98%, Due January 2026, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)