Binghatti Skyterraces construction progress

The registered completion date for Binghatti Skyterraces is October 2027. At the last site inspection, in October 2026, it was 7.0% built. The developer is Binghatti Developers.

7.0%

Built, at the site inspection of 28 October 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
July 2037
Construction started
January 2026
First registered
January 2026
Units
1,886
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي سكاي تيراسيز
Project number
4327
Site inspections
2

Schedule

Between January 2026 and October 2026 the site added about 0.7 points a month. At that rate it would finish around July 2037, more than three months after its registered date of October 2027.

0%25%50%75%100%2027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

7.0%+7.0 pts

  • Binghatti Skyterraces construction site, inspection photo 1, 28 October 2026
  • Binghatti Skyterraces construction site, inspection photo 2, 28 October 2026
  • Binghatti Skyterraces construction site, inspection photo 3, 28 October 2026
  • Binghatti Skyterraces construction site, inspection photo 4, 28 October 2026

7 January 2026

0%

  • Binghatti Skyterraces construction site, inspection photo 1, 7 January 2026
  • Binghatti Skyterraces construction site, inspection photo 2, 7 January 2026

All 9 site photos, by inspection date

Context

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Skyterraces?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Skyterraces handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Skyterraces?
Binghatti Skyterraces was 7.0% built at the site inspection on 28 October 2026. The site has been inspected 2 times since January 2026. The Land Department took 9 site photos at its inspections.
Is Binghatti Skyterraces delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Binghatti Skyterraces?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Skyterraces?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.