Binghatti Amberhall construction progress

Binghatti Amberhall in Jumeirah Village Circle was registered to complete in February 2026 and is still under construction. At the last site inspection, in October 2026, it was 70% built. The developer is Binghatti Developers.

70%

Built, at the site inspection of 26 October 2026

9 months past its registered completion date

Registered completion date
February 2026
Finish at recent pace
April 2027
Construction started
February 2025
First registered
March 2025
Units
710
Escrow bank
United Arab Bank
Name in Arabic
بن غاطي أمبر هول
Project number
3552
Site inspections
3

Schedule

Binghatti Amberhall was registered to complete in February 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 5.4 points a month. Kept at that rate, the site would reach 100% around April 2027.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

70%+32 pts

  • Binghatti Amberhall construction site, inspection photo 1, 26 October 2026
  • Binghatti Amberhall construction site, inspection photo 2, 26 October 2026
  • Binghatti Amberhall construction site, inspection photo 3, 26 October 2026
  • Binghatti Amberhall construction site, inspection photo 4, 26 October 2026

30 April 2026

38%+38 pts

  • Binghatti Amberhall construction site, inspection photo 1, 30 April 2026
  • Binghatti Amberhall construction site, inspection photo 2, 30 April 2026
  • Binghatti Amberhall construction site, inspection photo 3, 30 April 2026
  • Binghatti Amberhall construction site, inspection photo 4, 30 April 2026

11 February 2025

0%

  • Binghatti Amberhall construction site, inspection photo 1, 11 February 2025
  • Binghatti Amberhall construction site, inspection photo 2, 11 February 2025

All 22 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Amberhall?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Amberhall handover date?
The registered completion date was February 2026, and the register still lists Binghatti Amberhall as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Amberhall?
Binghatti Amberhall was 70% built at the site inspection on 26 October 2026. The site has been inspected 3 times since February 2025. The Land Department took 22 site photos at its inspections.
Is Binghatti Amberhall delayed?
Yes. Its registered completion date of February 2026 has passed and the project is still listed as under construction.
Who is building Binghatti Amberhall?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Amberhall?
United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.