Binghatti Amberhall construction progress

Binghatti Amberhall in Jumeirah Village Circle is 38% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for February 2026.

38%

Built, at the Land Department site inspection of 30 April 2026

7 months past its registered completion date

Completion date (Land Department)
February 2026
Finish at recent pace
April 2028
Construction started
February 2025
Registered with the Land Department
March 2025
Units
710
Escrow bank
United Arab Bank
Name in Arabic
بن غاطي أمبر هول
Land Department project number
3552
Land Department site inspections
2

Schedule

Binghatti Amberhall was registered to complete in February 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around April 2028.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 April 2026

38%+38 pts

  • Binghatti Amberhall construction site, Land Department inspection photo 1, 30 April 2026
  • Binghatti Amberhall construction site, Land Department inspection photo 2, 30 April 2026
  • Binghatti Amberhall construction site, Land Department inspection photo 3, 30 April 2026
  • Binghatti Amberhall construction site, Land Department inspection photo 4, 30 April 2026

11 February 2025

0%

  • Binghatti Amberhall construction site, Land Department inspection photo 1, 11 February 2025
  • Binghatti Amberhall construction site, Land Department inspection photo 2, 11 February 2025

All 9 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. Binghatti Amberhall is behind that average.

Binghatti Developers has 36 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Binghatti Amberhall?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Binghatti Amberhall be completed?
The completion date registered with the Dubai Land Department is February 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Binghatti Amberhall is built?
38%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 2 times since February 2025.
Is Binghatti Amberhall delayed?
Yes. Its registered completion date of February 2026 has passed and the Land Department still lists it as under construction.
Who is building Binghatti Amberhall?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Amberhall?
United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.