Binghatti Amberhall construction progress
Binghatti Amberhall in Jumeirah Village Circle is 38% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for February 2026.
38%
Built, at the Land Department site inspection of 30 April 2026
7 months past its registered completion date
- Completion date (Land Department)
- February 2026
- Finish at recent pace
- April 2028
- Construction started
- February 2025
- Registered with the Land Department
- March 2025
- Developer
- Binghatti Developers
- Community
- Jumeirah Village Circle
- Units
- 710
- Escrow bank
- United Arab Bank
- Name in Arabic
- بن غاطي أمبر هول
- Land Department project number
- 3552
- Land Department site inspections
- 2
Schedule
Binghatti Amberhall was registered to complete in February 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 2.6 points a month. Kept at that rate, the site would reach 100% around April 2028.
Site inspections
30 April 2026
38%+38 pts
11 February 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Binghatti Amberhall is behind that average.
Binghatti Developers has 36 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Binghatti Amberhall?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Binghatti Amberhall be completed?
- The completion date registered with the Dubai Land Department is February 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Amberhall is built?
- 38%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 2 times since February 2025.
- Is Binghatti Amberhall delayed?
- Yes. Its registered completion date of February 2026 has passed and the Land Department still lists it as under construction.
- Who is building Binghatti Amberhall?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Amberhall?
- United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.