Binghatti Hillviews construction progress

Binghatti Hillviews in Dubai Science Park was registered to complete in April 2026 and is still under construction. At the last site inspection, in June 2026, it was 33% built. The developer is Binghatti Developers.

33%

Built, at the site inspection of 25 June 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
March 2028
Construction started
October 2024
First registered
October 2024
Units
1,581
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
بن غاطي هيل فيوز
Project number
3321
Site inspections
3

Schedule

Binghatti Hillviews was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around March 2028.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 June 2026

33%+19 pts

  • Binghatti Hillviews construction site, inspection photo 1, 25 June 2026
  • Binghatti Hillviews construction site, inspection photo 2, 25 June 2026
  • Binghatti Hillviews construction site, inspection photo 3, 25 June 2026
  • Binghatti Hillviews construction site, inspection photo 4, 25 June 2026

31 December 2025

13%+13 pts

  • Binghatti Hillviews construction site, inspection photo 1, 31 December 2025
  • Binghatti Hillviews construction site, inspection photo 2, 31 December 2025
  • Binghatti Hillviews construction site, inspection photo 3, 31 December 2025
  • Binghatti Hillviews construction site, inspection photo 4, 31 December 2025

3 October 2024

0%

  • Binghatti Hillviews construction site, inspection photo 1, 3 October 2024
  • Binghatti Hillviews construction site, inspection photo 2, 3 October 2024
  • Binghatti Hillviews construction site, inspection photo 3, 3 October 2024

All 17 site photos, by inspection date

Context

Dubai Science Park has 10 projects under construction, 43% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Hillviews?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Hillviews handover date?
The registered completion date was April 2026, and the register still lists Binghatti Hillviews as under construction. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Hillviews?
Binghatti Hillviews was 33% built at the site inspection on 25 June 2026. The site has been inspected 3 times since October 2024. The Land Department took 17 site photos at its inspections.
Is Binghatti Hillviews delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Binghatti Hillviews?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Hillviews?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.