Binghatti Hillviews construction progress
Binghatti Hillviews in Dubai Science Park was registered to complete in April 2026 and is still under construction. At the last site inspection, in June 2026, it was 33% built. The developer is Binghatti Developers.
33%
Built, at the site inspection of 25 June 2026
8 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- March 2028
- Construction started
- October 2024
- First registered
- October 2024
- Developer
- Binghatti Developers
- Community
- Dubai Science Park
- Units
- 1,581
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- بن غاطي هيل فيوز
- Project number
- 3321
- Site inspections
- 3
Schedule
Binghatti Hillviews was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around March 2028.
Site inspections
25 June 2026
33%+19 pts
31 December 2025
13%+13 pts
3 October 2024
0%
Context
Dubai Science Park has 10 projects under construction, 43% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Hillviews?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Hillviews handover date?
- The registered completion date was April 2026, and the register still lists Binghatti Hillviews as under construction. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Hillviews?
- Binghatti Hillviews was 33% built at the site inspection on 25 June 2026. The site has been inspected 3 times since October 2024. The Land Department took 17 site photos at its inspections.
- Is Binghatti Hillviews delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Binghatti Hillviews?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Hillviews?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Vincitore Aqua DimoreNearby in Dubai Science Park. 14%.
- Vincitore Aqua FloraNearby in Dubai Science Park. 1.3%, Due June 2028.
- Empire LivingsNearby in Dubai Science Park. 13%, Due November 2027.
- Saas HillsNearby in Dubai Science Park. 17%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)