Binghatti Circle construction progress

The registered completion date for Binghatti Circle in Jumeirah Village Circle is May 2027. At the last site inspection, in October 2026, it was 22% built. The developer is Binghatti Developers.

22%

Built, at the site inspection of 26 October 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
January 2030
Construction started
June 2025
First registered
July 2025
Units
822
Escrow bank
Dubai Islamic Bank
Name in Arabic
بن غاطي سيركل
Project number
3819
Site inspections
3

Schedule

Between April 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around January 2030, more than three months after its registered date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

22%+12 pts

  • Binghatti Circle construction site, inspection photo 1, 26 October 2026
  • Binghatti Circle construction site, inspection photo 2, 26 October 2026
  • Binghatti Circle construction site, inspection photo 3, 26 October 2026
  • Binghatti Circle construction site, inspection photo 4, 26 October 2026

30 April 2026

10%+10 pts

  • Binghatti Circle construction site, inspection photo 1, 30 April 2026
  • Binghatti Circle construction site, inspection photo 2, 30 April 2026
  • Binghatti Circle construction site, inspection photo 3, 30 April 2026
  • Binghatti Circle construction site, inspection photo 4, 30 April 2026

23 June 2025

0%

  • Binghatti Circle construction site, inspection photo 1, 23 June 2025
  • Binghatti Circle construction site, inspection photo 2, 23 June 2025

All 19 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Circle?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Circle handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Circle?
Binghatti Circle was 22% built at the site inspection on 26 October 2026. The site has been inspected 3 times since June 2025. The Land Department took 19 site photos at its inspections.
Is Binghatti Circle delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Binghatti Circle?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Circle?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.