Binghatti Circle construction progress
The registered completion date for Binghatti Circle in Jumeirah Village Circle is May 2027. At the last site inspection, in October 2026, it was 22% built. The developer is Binghatti Developers.
22%
Built, at the site inspection of 26 October 2026
Running behind its date
- Registered completion date
- May 2027
- Finish at recent pace
- January 2030
- Construction started
- June 2025
- First registered
- July 2025
- Developer
- Binghatti Developers
- Community
- Jumeirah Village Circle
- Units
- 822
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي سيركل
- Project number
- 3819
- Site inspections
- 3
Schedule
Between April 2026 and October 2026 the site added about 2.0 points a month. At that rate it would finish around January 2030, more than three months after its registered date of May 2027.
Site inspections
26 October 2026
22%+12 pts
30 April 2026
10%+10 pts
23 June 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Circle?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Circle handover date?
- The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Circle?
- Binghatti Circle was 22% built at the site inspection on 26 October 2026. The site has been inspected 3 times since June 2025. The Land Department took 19 site photos at its inspections.
- Is Binghatti Circle delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
- Who is building Binghatti Circle?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Circle?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.