Binghatti Circle construction progress
Binghatti Circle in Jumeirah Village Circle is 10% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for May 2027.
10%
Built, at the Land Department site inspection of 30 April 2026
Running behind its date
- Completion date (Land Department)
- May 2027
- Finish at recent pace
- September 2033
- Construction started
- June 2025
- Registered with the Land Department
- July 2025
- Developer
- Binghatti Developers
- Community
- Jumeirah Village Circle
- Units
- 822
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي سيركل
- Land Department project number
- 3819
- Land Department site inspections
- 2
Schedule
Between June 2025 and April 2026 the site added about 1.0 points a month. At that rate it would finish around September 2033, more than three months after the May 2027 date registered with the Land Department.
Site inspections
30 April 2026
10%+10 pts
23 June 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Binghatti Circle is behind that average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Binghatti Circle?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Binghatti Circle be completed?
- The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around September 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Binghatti Circle is built?
- 10%, measured at the Land Department site inspection on 30 April 2026. The Land Department engineers have inspected the site 2 times since June 2025.
- Is Binghatti Circle delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
- Who is building Binghatti Circle?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Circle?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.