Binghatti Moonlight construction progress
Binghatti Moonlight in Jaddaf Waterfront was registered to complete in June 2026 and is still under construction. At the last site inspection, in June 2026, it was 19% built. The developer is Binghatti Developers.
19%
Built, at the site inspection of 29 June 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- May 2031
- Construction started
- April 2025
- First registered
- June 2025
- Developer
- Binghatti Developers
- Community
- Jaddaf Waterfront
- Units
- 286
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- بن غاطي مونلايت
- Project number
- 3722
- Site inspections
- 2
Schedule
Binghatti Moonlight was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.4 points a month. Kept at that rate, the site would reach 100% around May 2031.
Site inspections
29 June 2026
19%+19 pts
29 April 2025
0%
Context
Jaddaf Waterfront has 13 projects under construction, 32% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Moonlight?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Moonlight handover date?
- The registered completion date was June 2026, and the register still lists Binghatti Moonlight as under construction. At the pace of its recent inspections the site would reach 100% around May 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Moonlight?
- Binghatti Moonlight was 19% built at the site inspection on 29 June 2026. The site has been inspected 2 times since April 2025. The Land Department took 9 site photos at its inspections.
- Is Binghatti Moonlight delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Binghatti Moonlight?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Moonlight?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Cascade VilleNearby in Jaddaf Waterfront. 22%, Due December 2027.
- Boutique 23Nearby in Jaddaf Waterfront. 65%.
- Art Bay EastNearby in Jaddaf Waterfront. 19%.
- Art Bay WestNearby in Jaddaf Waterfront. 15%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.