Binghatti Twilight construction progress
Binghatti Twilight in Jaddaf Waterfront was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 55% built. The developer is Binghatti Developers.
55%
Built, at the site inspection of 14 September 2026
7 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- June 2027
- Construction started
- April 2025
- First registered
- June 2025
- Developer
- Binghatti Developers
- Community
- Jaddaf Waterfront
- Units
- 277
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- بن غاطي توايلايت
- Project number
- 3397
- Site inspections
- 3
Schedule
Binghatti Twilight was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 5.2 points a month. Kept at that rate, the site would reach 100% around June 2027.
Site inspections
14 September 2026
55%+23 pts
30 April 2026
32%+32 pts
14 November 2024
0%
Context
Jaddaf Waterfront has 13 projects under construction, 32% built on average.
Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.
Own a unit in Binghatti Twilight?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Binghatti Twilight handover date?
- The registered completion date was April 2026, and the register still lists Binghatti Twilight as under construction. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Binghatti Twilight?
- Binghatti Twilight was 55% built at the site inspection on 14 September 2026. The site has been inspected 3 times since November 2024. The Land Department took 17 site photos at its inspections.
- Is Binghatti Twilight delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Binghatti Twilight?
- The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
- Which bank holds the escrow account for Binghatti Twilight?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Mercedes-Benz Places | BinghattiAlso by Binghatti Developers. 65%, Due December 2026.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- Cascade VilleNearby in Jaddaf Waterfront. 22%, Due December 2027.
- Boutique 23Nearby in Jaddaf Waterfront. 65%.
- Art Bay EastNearby in Jaddaf Waterfront. 19%.
- Art Bay WestNearby in Jaddaf Waterfront. 15%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)