Binghatti Twilight construction progress

Binghatti Twilight in Jaddaf Waterfront was registered to complete in April 2026 and is still under construction. At the last site inspection, in September 2026, it was 55% built. The developer is Binghatti Developers.

55%

Built, at the site inspection of 14 September 2026

7 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
June 2027
Construction started
April 2025
First registered
June 2025
Units
277
Escrow bank
Sharjah Islamic Bank
Name in Arabic
بن غاطي توايلايت
Project number
3397
Site inspections
3

Schedule

Binghatti Twilight was registered to complete in April 2026, 7 months ago, and is still under construction. Over the last year of inspections it has added about 5.2 points a month. Kept at that rate, the site would reach 100% around June 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 September 2026

55%+23 pts

  • Binghatti Twilight construction site, inspection photo 1, 14 September 2026
  • Binghatti Twilight construction site, inspection photo 2, 14 September 2026
  • Binghatti Twilight construction site, inspection photo 3, 14 September 2026
  • Binghatti Twilight construction site, inspection photo 4, 14 September 2026

30 April 2026

32%+32 pts

  • Binghatti Twilight construction site, inspection photo 1, 30 April 2026
  • Binghatti Twilight construction site, inspection photo 2, 30 April 2026
  • Binghatti Twilight construction site, inspection photo 3, 30 April 2026
  • Binghatti Twilight construction site, inspection photo 4, 30 April 2026

14 November 2024

0%

  • Binghatti Twilight construction site, inspection photo 1, 14 November 2024
  • Binghatti Twilight construction site, inspection photo 2, 14 November 2024

All 17 site photos, by inspection date

Context

Jaddaf Waterfront has 13 projects under construction, 32% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Binghatti Twilight?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Binghatti Twilight handover date?
The registered completion date was April 2026, and the register still lists Binghatti Twilight as under construction. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Binghatti Twilight?
Binghatti Twilight was 55% built at the site inspection on 14 September 2026. The site has been inspected 3 times since November 2024. The Land Department took 17 site photos at its inspections.
Is Binghatti Twilight delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Binghatti Twilight?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Binghatti Twilight?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.