Mercedes-Benz Places | Binghatti construction progress
Mercedes-Benz Places | Binghatti in DownTown Dubai is 65% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for December 2026.
65%
Built, at the Land Department site inspection of 28 April 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- June 2027
- Construction started
- December 2023
- Registered with the Land Department
- December 2023
- Developer
- Binghatti Developers
- Community
- DownTown Dubai
- Units
- 163
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- مرسيدس-بنز بليسز | بن غاطي
- Land Department project number
- 2545
- Land Department site inspections
- 4
Schedule
Between October 2025 and April 2026 the site added about 2.6 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
28 April 2026
65%+17 pts
14 October 2025
48%+22 pts
23 January 2025
26%+26 pts
4 January 2023
0%
Context
DownTown Dubai has 13 projects under construction, 33% built on average.
Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.
Own a unit in Mercedes-Benz Places | Binghatti?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Mercedes-Benz Places | Binghatti be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mercedes-Benz Places | Binghatti is built?
- 65%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 4 times since January 2023.
- Is Mercedes-Benz Places | Binghatti delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Mercedes-Benz Places | Binghatti?
- The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
- Which bank holds the escrow account for Mercedes-Benz Places | Binghatti?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Burj Binghatti Jacob & Co. ResidencesAlso by Binghatti Developers. 52%, Due June 2026, passed.
- Bugatti Residences By BinghattiAlso by Binghatti Developers. 66%, Due December 2025, passed.
- Binghatti HillsAlso by Binghatti Developers. 90%.
- One By BinghattiAlso by Binghatti Developers. 50%.
- The St. Regis Residences, Downtown DubaiNearby in DownTown Dubai. 76%, Due December 2026.
- City Center ResidencesNearby in DownTown Dubai. 72%, Due September 2026, passed.
- Baccarat Hotel And Residences, DubaiNearby in DownTown Dubai. 21%.
- Rove Home Residences By IrthNearby in DownTown Dubai. 63%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)