Mercedes-Benz Places | Binghatti construction progress

The registered completion date for Mercedes-Benz Places | Binghatti in DownTown Dubai is December 2026. At the last site inspection, in April 2026, it was 65% built. The developer is Binghatti Developers.

65%

Built, at the site inspection of 28 April 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
June 2027
Construction started
December 2023
First registered
December 2023
Units
163
Escrow bank
Sharjah Islamic Bank
Name in Arabic
مرسيدس-بنز بليسز | بن غاطي
Project number
2545
Site inspections
4

Schedule

Between October 2025 and April 2026 the site added about 2.6 points a month. At that rate it would finish around June 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 April 2026

65%+17 pts

  • Mercedes-Benz Places | Binghatti construction site, inspection photo 1, 28 April 2026
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 2, 28 April 2026
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 3, 28 April 2026
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 4, 28 April 2026

14 October 2025

48%+22 pts

  • Mercedes-Benz Places | Binghatti construction site, inspection photo 1, 14 October 2025
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 2, 14 October 2025
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 3, 14 October 2025
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 4, 14 October 2025

23 January 2025

26%+26 pts

  • Mercedes-Benz Places | Binghatti construction site, inspection photo 1, 23 January 2025
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 2, 23 January 2025
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 3, 23 January 2025
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 4, 23 January 2025

4 January 2023

0%

  • Mercedes-Benz Places | Binghatti construction site, inspection photo 1, 4 January 2023
  • Mercedes-Benz Places | Binghatti construction site, inspection photo 2, 4 January 2023

All 26 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 35% built on average.

Binghatti Developers has 38 projects under construction in Dubai; 14 have passed their registered completion date.

Own a unit in Mercedes-Benz Places | Binghatti?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mercedes-Benz Places | Binghatti handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mercedes-Benz Places | Binghatti?
Mercedes-Benz Places | Binghatti was 65% built at the site inspection on 28 April 2026. The site has been inspected 4 times since January 2023. The Land Department took 26 site photos at its inspections.
Is Mercedes-Benz Places | Binghatti delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Mercedes-Benz Places | Binghatti?
The registered developer is Binghatti Developers. It has 37 other projects under construction in Dubai.
Which bank holds the escrow account for Mercedes-Benz Places | Binghatti?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.