Mercedes-Benz Places | Binghatti construction progress

Mercedes-Benz Places | Binghatti in DownTown Dubai is 65% built at the Land Department inspection of April 2026. Developer Binghatti Developers. Completion registered for December 2026.

65%

Built, at the Land Department site inspection of 28 April 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
June 2027
Construction started
December 2023
Registered with the Land Department
December 2023
Units
163
Escrow bank
Sharjah Islamic Bank
Name in Arabic
مرسيدس-بنز بليسز | بن غاطي
Land Department project number
2545
Land Department site inspections
4

Schedule

Between October 2025 and April 2026 the site added about 2.6 points a month. At that rate it would finish around June 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 April 2026

65%+17 pts

  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 1, 28 April 2026
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 2, 28 April 2026
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 3, 28 April 2026
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 4, 28 April 2026

14 October 2025

48%+22 pts

  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 1, 14 October 2025
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 2, 14 October 2025
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 3, 14 October 2025
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 4, 14 October 2025

23 January 2025

26%+26 pts

  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 1, 23 January 2025
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 2, 23 January 2025
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 3, 23 January 2025
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 4, 23 January 2025

4 January 2023

0%

  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 1, 4 January 2023
  • Mercedes-Benz Places | Binghatti construction site, Land Department inspection photo 2, 4 January 2023

All 26 site photos, by inspection date

Context

DownTown Dubai has 13 projects under construction, 33% built on average.

Binghatti Developers has 36 projects under construction in Dubai; 11 have passed their registered completion date.

Own a unit in Mercedes-Benz Places | Binghatti?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mercedes-Benz Places | Binghatti be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mercedes-Benz Places | Binghatti is built?
65%, measured at the Land Department site inspection on 28 April 2026. The Land Department engineers have inspected the site 4 times since January 2023.
Is Mercedes-Benz Places | Binghatti delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Mercedes-Benz Places | Binghatti?
The registered developer is Binghatti Developers. It has 35 other projects under construction in Dubai.
Which bank holds the escrow account for Mercedes-Benz Places | Binghatti?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.