Off-plan projects in Jumeirah Garden City
27 projects in Jumeirah Garden City are under construction according to the Dubai Land Department. On average they are 30% built. 9 have passed their registered completion date. The next one due is Stamn One, in October 2026.
- Brand CentroE M S Real Estate Development90%Due July 2026, passed
- The GrandalaPalladium Prime Real Estate Development86%Due January 2026, passed
- Mayfair Gardens By MajidMajid Developments70%No date set
- 161 Jumeirah LaneNational Properties70%No date set
- Trillium HeightsGrenorbit Real Estate Development62%Due December 2025, passed
- Evergrin HouseObj1 Real Estate Development55%Due June 2026, passed
- Jardin AstralGalaxy Realty45%Due August 2026, passed
- Rose Gardens 1Cavara Real Estate Development43%Due July 2026, passed
- Enso JadeEnso Development42%Due June 2026, passed
- Stamn OneStamn Real Estate Development42%Due October 2026
- Onaya Residences By KayaKaya Properties38%Due June 2026, passed
- 171 Garden HeightsJad Global Real Estate Development34%Due December 2026
- Alba TowerCentury Seven Properties31%Due June 2028
- Purvanchal Triana ResidencesPurvanchal Real Estate Developers26%Due March 2027
- Elemental 22Elemental Developments26%Due May 2028
- Stamn YuniStamn Real Estate Development12%Due March 2027
- Enso AmberEnso Development11%Due June 2026, passed
- Chelsea GardensAlaia Developments10%Due February 2027
- Evergrin House 2Obj1 Real Estate Development10%Due December 2026
- Olivia Gardens ResidenceSegrex Terra Development5.5%Due April 2027
- The ElysianNew M F O U R Real Estate Development4.5%Due August 2027
- Whitestone ResidenceAxiom Prime Real Estate Development3.0%Due October 2026
- West 5 ResidencesWest F 5 Development2.8%No date set
- Jad 288Jad Global Real Estate Development1.9%Due December 2027
- VibeArsenal East Real Estate Development1.5%Due August 2028
- ElmoraNeoterra Real Estate Development0%Due February 2028
- Villea WestPalmridge Real Estate Development0%Due November 2027
Reading these figures
Each percentage is the share of construction Land Department engineers recorded at their latest site visit. The completion date is the one the developer registered with the Land Department, and developers can apply to move it. Open a project to see its latest inspections, the site photos and whether it is keeping pace with that date.
What happens at handover and how to snag a new home cover the steps after 100%.
Source: the Dubai Land Department’s Mashrooi register, read daily. Projects listed as cancelled or finished are not shown.