Jardin Astral construction progress

Jardin Astral in Jumeirah Garden City is 45% built at the Land Department inspection of May 2026. Developer Galaxy Realty. Completion registered for August 2026.

45%

Built, at the Land Department site inspection of 18 May 2026

2 months past its registered completion date

Completion date (Land Department)
August 2026
Finish at recent pace
July 2027
Construction started
August 2024
Registered with the Land Department
May 2024
Developer
Galaxy Realty
Units
44
Escrow bank
Emirates NBD
Name in Arabic
جردن أسترل
Land Department project number
3061
Land Department site inspections
5

Schedule

Jardin Astral was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.9 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 May 2026

45%+25 pts

  • Jardin Astral construction site, Land Department inspection photo 1, 18 May 2026
  • Jardin Astral construction site, Land Department inspection photo 2, 18 May 2026
  • Jardin Astral construction site, Land Department inspection photo 3, 18 May 2026
  • Jardin Astral construction site, Land Department inspection photo 4, 18 May 2026

30 December 2025

20%+13 pts

  • Jardin Astral construction site, Land Department inspection photo 1, 30 December 2025
  • Jardin Astral construction site, Land Department inspection photo 2, 30 December 2025
  • Jardin Astral construction site, Land Department inspection photo 3, 30 December 2025
  • Jardin Astral construction site, Land Department inspection photo 4, 30 December 2025

24 July 2025

6.6%+1.5 pts

  • Jardin Astral construction site, Land Department inspection photo 1, 24 July 2025
  • Jardin Astral construction site, Land Department inspection photo 2, 24 July 2025
  • Jardin Astral construction site, Land Department inspection photo 3, 24 July 2025
  • Jardin Astral construction site, Land Department inspection photo 4, 24 July 2025

6 March 2025

5.1%+5.1 pts

  • Jardin Astral construction site, Land Department inspection photo 1, 6 March 2025
  • Jardin Astral construction site, Land Department inspection photo 2, 6 March 2025
  • Jardin Astral construction site, Land Department inspection photo 3, 6 March 2025
  • Jardin Astral construction site, Land Department inspection photo 4, 6 March 2025

6 May 2024

0%

  • Jardin Astral construction site, Land Department inspection photo 1, 6 May 2024
  • Jardin Astral construction site, Land Department inspection photo 2, 6 May 2024
  • Jardin Astral construction site, Land Department inspection photo 3, 6 May 2024

All 32 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Jardin Astral?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Jardin Astral be completed?
The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Jardin Astral is built?
45%, measured at the Land Department site inspection on 18 May 2026. The Land Department engineers have inspected the site 5 times since May 2024.
Is Jardin Astral delayed?
Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
Who is building Jardin Astral?
The registered developer is Galaxy Realty.
Which bank holds the escrow account for Jardin Astral?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.