Jardin Astral construction progress
Jardin Astral in Jumeirah Garden City is 45% built at the Land Department inspection of May 2026. Developer Galaxy Realty. Completion registered for August 2026.
45%
Built, at the Land Department site inspection of 18 May 2026
2 months past its registered completion date
- Completion date (Land Department)
- August 2026
- Finish at recent pace
- July 2027
- Construction started
- August 2024
- Registered with the Land Department
- May 2024
- Developer
- Galaxy Realty
- Community
- Jumeirah Garden City
- Units
- 44
- Escrow bank
- Emirates NBD
- Name in Arabic
- جردن أسترل
- Land Department project number
- 3061
- Land Department site inspections
- 5
Schedule
Jardin Astral was registered to complete in August 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.9 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
18 May 2026
45%+25 pts
30 December 2025
20%+13 pts
24 July 2025
6.6%+1.5 pts
6 March 2025
5.1%+5.1 pts
6 May 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 30% built on average.
Own a unit in Jardin Astral?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Jardin Astral be completed?
- The completion date registered with the Dubai Land Department is August 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Jardin Astral is built?
- 45%, measured at the Land Department site inspection on 18 May 2026. The Land Department engineers have inspected the site 5 times since May 2024.
- Is Jardin Astral delayed?
- Yes. Its registered completion date of August 2026 has passed and the Land Department still lists it as under construction.
- Who is building Jardin Astral?
- The registered developer is Galaxy Realty.
- Which bank holds the escrow account for Jardin Astral?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 86%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 31%, Due June 2028.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- 161 Jumeirah LaneNearby in Jumeirah Garden City. 70%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.