Chelsea Gardens construction progress

Chelsea Gardens in Jumeirah Garden City is 10% built at the Land Department inspection of September 2026. Developer Alaia Developments. Completion registered for February 2027.

10%

Built, at the Land Department site inspection of 23 September 2026

Running behind its date

Completion date (Land Department)
February 2027
Finish at recent pace
September 2034
Construction started
March 2025
Registered with the Land Department
April 2025
Developer
Alaia Developments
Units
59
Escrow bank
Mashreq Bank
Name in Arabic
تشيلسي جاردنز
Land Department project number
3553
Land Department site inspections
4

Schedule

Between December 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around September 2034, more than three months after the February 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 September 2026

10%+7.1 pts

  • Chelsea Gardens construction site, Land Department inspection photo 1, 23 September 2026
  • Chelsea Gardens construction site, Land Department inspection photo 2, 23 September 2026
  • Chelsea Gardens construction site, Land Department inspection photo 3, 23 September 2026
  • Chelsea Gardens construction site, Land Department inspection photo 4, 23 September 2026

12 May 2026

3.2%+1.2 pts

  • Chelsea Gardens construction site, Land Department inspection photo 1, 12 May 2026
  • Chelsea Gardens construction site, Land Department inspection photo 2, 12 May 2026
  • Chelsea Gardens construction site, Land Department inspection photo 3, 12 May 2026
  • Chelsea Gardens construction site, Land Department inspection photo 4, 12 May 2026

30 December 2025

2.0%+2.0 pts

  • Chelsea Gardens construction site, Land Department inspection photo 1, 30 December 2025
  • Chelsea Gardens construction site, Land Department inspection photo 2, 30 December 2025

7 February 2025

0%

  • Chelsea Gardens construction site, Land Department inspection photo 1, 7 February 2025
  • Chelsea Gardens construction site, Land Department inspection photo 2, 7 February 2025

All 14 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Chelsea Gardens?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Chelsea Gardens be completed?
The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around September 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Chelsea Gardens is built?
10%, measured at the Land Department site inspection on 23 September 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is Chelsea Gardens delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
Who is building Chelsea Gardens?
The registered developer is Alaia Developments.
Which bank holds the escrow account for Chelsea Gardens?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.