Vibe construction progress

The registered completion date for Vibe in Jumeirah Garden City is August 2028. At the last site inspection, in April 2026, it was 1.5% built. The developer is Arsenal East Real Estate Development.

1.5%

Built, at the site inspection of 9 April 2026

Running behind its date

Registered completion date
August 2028
Finish at recent pace
June 2064
Construction started
October 2025
First registered
January 2026
Developer
Arsenal East Real Estate Development
Units
212
Escrow bank
First Abu Dhabi Bank
Name in Arabic
?ايب
Project number
4083
Site inspections
2

Schedule

Between September 2025 and April 2026 the site added about 0.2 points a month. At that rate it would finish around June 2064, more than three months after its registered date of August 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 April 2026

1.5%+1.5 pts

  • Vibe construction site, inspection photo 1, 9 April 2026
  • Vibe construction site, inspection photo 2, 9 April 2026
  • Vibe construction site, inspection photo 3, 9 April 2026
  • Vibe construction site, inspection photo 4, 9 April 2026

10 September 2025

0%

  • Vibe construction site, inspection photo 1, 10 September 2025
  • Vibe construction site, inspection photo 2, 10 September 2025

All 6 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Arsenal East Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vibe?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Vibe handover date?
The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2064. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Vibe?
Vibe was 1.5% built at the site inspection on 9 April 2026. The site has been inspected 2 times since September 2025. The Land Department took 6 site photos at its inspections.
Is Vibe delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Vibe?
The registered developer is Arsenal East Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Vibe?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.