Vibe construction progress

Vibe in Jumeirah Garden City is 1.5% built at the Land Department inspection of April 2026. Developer Arsenal East Real Estate Development. Completion registered for August 2028.

1.5%

Built, at the Land Department site inspection of 9 April 2026

Running behind its date

Completion date (Land Department)
August 2028
Finish at recent pace
June 2064
Construction started
October 2025
Registered with the Land Department
January 2026
Developer
Arsenal East Real Estate Development
Units
212
Escrow bank
First Abu Dhabi Bank
Name in Arabic
?ايب
Land Department project number
4083
Land Department site inspections
2

Schedule

Between September 2025 and April 2026 the site added about 0.2 points a month. At that rate it would finish around June 2064, more than three months after the August 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 April 2026

1.5%+1.5 pts

  • Vibe construction site, Land Department inspection photo 1, 9 April 2026
  • Vibe construction site, Land Department inspection photo 2, 9 April 2026
  • Vibe construction site, Land Department inspection photo 3, 9 April 2026
  • Vibe construction site, Land Department inspection photo 4, 9 April 2026

10 September 2025

0%

  • Vibe construction site, Land Department inspection photo 1, 10 September 2025
  • Vibe construction site, Land Department inspection photo 2, 10 September 2025

All 6 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average. Vibe is behind that average.

Arsenal East Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Vibe?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Vibe be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around June 2064. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vibe is built?
1.5%, measured at the Land Department site inspection on 9 April 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Vibe delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Vibe?
The registered developer is Arsenal East Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Vibe?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.