Vibe construction progress
Vibe in Jumeirah Garden City is 1.5% built at the Land Department inspection of April 2026. Developer Arsenal East Real Estate Development. Completion registered for August 2028.
1.5%
Built, at the Land Department site inspection of 9 April 2026
Running behind its date
- Completion date (Land Department)
- August 2028
- Finish at recent pace
- June 2064
- Construction started
- October 2025
- Registered with the Land Department
- January 2026
- Developer
- Arsenal East Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 212
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ?ايب
- Land Department project number
- 4083
- Land Department site inspections
- 2
Schedule
Between September 2025 and April 2026 the site added about 0.2 points a month. At that rate it would finish around June 2064, more than three months after the August 2028 date registered with the Land Department.
Site inspections
9 April 2026
1.5%+1.5 pts
10 September 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 30% built on average. Vibe is behind that average.
Arsenal East Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Vibe?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Vibe be completed?
- The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around June 2064. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Vibe is built?
- 1.5%, measured at the Land Department site inspection on 9 April 2026. The Land Department engineers have inspected the site 2 times since September 2025.
- Is Vibe delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
- Who is building Vibe?
- The registered developer is Arsenal East Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Vibe?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Zephyra ResidencesAlso by Arsenal East Real Estate Development. 31%, Due December 2027.
- The GrandalaNearby in Jumeirah Garden City. 86%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 31%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)