West 5 Residences construction progress

The registered completion date for West 5 Residences in Jumeirah Garden City is April 2027. At the last site inspection, in October 2026, it was 8.2% built. The developer is West F 5 Development.

8.2%

Built, at the site inspection of 19 October 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
July 2035
Construction started
April 2025
First registered
April 2025
Developer
West F 5 Development
Units
130
Escrow bank
Emirates Islamic Bank
Name in Arabic
ويست 5 ريزدنسز
Project number
3521
Site inspections
4

Schedule

Between January 2026 and October 2026 the site added about 0.9 points a month. At that rate it would finish around July 2035, more than three months after its registered date of April 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 October 2026

8.2%+5.4 pts

  • West 5 Residences construction site, inspection photo 1, 19 October 2026
  • West 5 Residences construction site, inspection photo 2, 19 October 2026
  • West 5 Residences construction site, inspection photo 3, 19 October 2026
  • West 5 Residences construction site, inspection photo 4, 19 October 2026

28 July 2026

2.8%+2.7 pts

  • West 5 Residences construction site, inspection photo 1, 28 July 2026
  • West 5 Residences construction site, inspection photo 2, 28 July 2026
  • West 5 Residences construction site, inspection photo 3, 28 July 2026
  • West 5 Residences construction site, inspection photo 4, 28 July 2026

9 January 2026

0.1%+0.1 pts

  • West 5 Residences construction site, inspection photo 1, 9 January 2026
  • West 5 Residences construction site, inspection photo 2, 9 January 2026
  • West 5 Residences construction site, inspection photo 3, 9 January 2026
  • West 5 Residences construction site, inspection photo 4, 9 January 2026

13 February 2025

0%

  • West 5 Residences construction site, inspection photo 1, 13 February 2025
  • West 5 Residences construction site, inspection photo 2, 13 February 2025

All 20 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in West 5 Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the West 5 Residences handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on West 5 Residences?
West 5 Residences was 8.2% built at the site inspection on 19 October 2026. The site has been inspected 4 times since February 2025. The Land Department took 20 site photos at its inspections.
Is West 5 Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building West 5 Residences?
The registered developer is West F 5 Development.
Which bank holds the escrow account for West 5 Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.