Enso Amber construction progress

Enso Amber in Jumeirah Garden City was registered to complete in June 2026 and is still under construction. At the last site inspection, in July 2026, it was 11% built. The developer is Enso Development.

11%

Built, at the site inspection of 14 July 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
June 2031
Construction started
September 2024
First registered
October 2024
Developer
Enso Development
Units
71
Escrow bank
Mashreq Bank
Name in Arabic
إنسو عنبر
Project number
3250
Site inspections
4

Schedule

Enso Amber was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around June 2031.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

11%+6.0 pts

  • Enso Amber construction site, inspection photo 1, 14 July 2026
  • Enso Amber construction site, inspection photo 2, 14 July 2026
  • Enso Amber construction site, inspection photo 3, 14 July 2026
  • Enso Amber construction site, inspection photo 4, 14 July 2026

13 April 2026

5.3%+3.2 pts

  • Enso Amber construction site, inspection photo 1, 13 April 2026
  • Enso Amber construction site, inspection photo 2, 13 April 2026
  • Enso Amber construction site, inspection photo 3, 13 April 2026

8 January 2026

2.1%+2.1 pts

  • Enso Amber construction site, inspection photo 1, 8 January 2026
  • Enso Amber construction site, inspection photo 2, 8 January 2026
  • Enso Amber construction site, inspection photo 3, 8 January 2026
  • Enso Amber construction site, inspection photo 4, 8 January 2026

10 September 2024

0%

  • Enso Amber construction site, inspection photo 1, 10 September 2024
  • Enso Amber construction site, inspection photo 2, 10 September 2024

All 16 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Enso Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Enso Amber?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Enso Amber handover date?
The registered completion date was June 2026, and the register still lists Enso Amber as under construction. At the pace of its recent inspections the site would reach 100% around June 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Enso Amber?
Enso Amber was 11% built at the site inspection on 14 July 2026. The site has been inspected 4 times since September 2024. The Land Department took 16 site photos at its inspections.
Is Enso Amber delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Enso Amber?
The registered developer is Enso Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Enso Amber?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.