Skip to content

Enso Amber construction progress

Enso Amber in Jumeirah Garden City is 11% built at the Land Department inspection of July 2026. Developer Enso Development. Completion registered for June 2026.

11%

Built, at the Land Department site inspection of 14 July 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
June 2031
Construction started
September 2024
Registered with the Land Department
October 2024
Developer
Enso Development
Units
71
Escrow bank
Mashreq Bank
Name in Arabic
إنسو عنبر
Land Department project number
3250
Land Department site inspections
4

Schedule

Enso Amber was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 1.5 points a month. Kept at that rate, the site would reach 100% around June 2031.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 July 2026

11%+6.0 pts

  • Enso Amber construction site, Land Department inspection photo 1, 14 July 2026
  • Enso Amber construction site, Land Department inspection photo 2, 14 July 2026
  • Enso Amber construction site, Land Department inspection photo 3, 14 July 2026
  • Enso Amber construction site, Land Department inspection photo 4, 14 July 2026

13 April 2026

5.3%+3.2 pts

  • Enso Amber construction site, Land Department inspection photo 1, 13 April 2026
  • Enso Amber construction site, Land Department inspection photo 2, 13 April 2026
  • Enso Amber construction site, Land Department inspection photo 3, 13 April 2026

8 January 2026

2.1%+2.1 pts

  • Enso Amber construction site, Land Department inspection photo 1, 8 January 2026
  • Enso Amber construction site, Land Department inspection photo 2, 8 January 2026
  • Enso Amber construction site, Land Department inspection photo 3, 8 January 2026
  • Enso Amber construction site, Land Department inspection photo 4, 8 January 2026

10 September 2024

0%

  • Enso Amber construction site, Land Department inspection photo 1, 10 September 2024
  • Enso Amber construction site, Land Department inspection photo 2, 10 September 2024

All 16 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Enso Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Enso Amber?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Enso Amber be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around June 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Enso Amber is built?
11%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 4 times since September 2024.
Is Enso Amber delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Enso Amber?
The registered developer is Enso Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Enso Amber?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.