Alba Tower construction progress

Alba Tower in Jumeirah Garden City is 31% built at the Land Department inspection of July 2026. Developer Century Seven Properties. Completion registered for June 2028.

31%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
June 2028
Finish at recent pace
November 2028
Construction started
September 2024
Registered with the Land Department
August 2024
Developer
Century Seven Properties
Units
73
Escrow bank
Commercial Bank of Dubai
Name in Arabic
البا تاور
Land Department project number
3059
Land Department site inspections
4

Schedule

Between February 2026 and July 2026 the site added about 2.5 points a month. At that rate it would finish around November 2028, more than three months after the June 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

31%+13 pts

  • Alba Tower construction site, Land Department inspection photo 1, 27 July 2026
  • Alba Tower construction site, Land Department inspection photo 2, 27 July 2026
  • Alba Tower construction site, Land Department inspection photo 3, 27 July 2026
  • Alba Tower construction site, Land Department inspection photo 4, 27 July 2026

24 February 2026

18%+17 pts

  • Alba Tower construction site, Land Department inspection photo 1, 24 February 2026
  • Alba Tower construction site, Land Department inspection photo 2, 24 February 2026
  • Alba Tower construction site, Land Department inspection photo 3, 24 February 2026
  • Alba Tower construction site, Land Department inspection photo 4, 24 February 2026

26 June 2025

1.2%+1.2 pts

  • Alba Tower construction site, Land Department inspection photo 1, 26 June 2025
  • Alba Tower construction site, Land Department inspection photo 2, 26 June 2025
  • Alba Tower construction site, Land Department inspection photo 3, 26 June 2025
  • Alba Tower construction site, Land Department inspection photo 4, 26 June 2025

23 May 2024

0%

  • Alba Tower construction site, Land Department inspection photo 1, 23 May 2024
  • Alba Tower construction site, Land Department inspection photo 2, 23 May 2024

All 19 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Alba Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Alba Tower be completed?
The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around November 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Alba Tower is built?
31%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 4 times since May 2024.
Is Alba Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Alba Tower?
The registered developer is Century Seven Properties.
Which bank holds the escrow account for Alba Tower?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.