Alba Tower construction progress

The registered completion date for Alba Tower in Jumeirah Garden City is June 2028. At the last site inspection, in July 2026, it was 31% built. The developer is Century Seven Properties.

42%

Built, at the site inspection of 27 July 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
November 2028
Construction started
September 2024
First registered
August 2024
Developer
Century Seven Properties
Units
73
Escrow bank
Commercial Bank of Dubai
Name in Arabic
البا تاور
Project number
3059
Site inspections
4

Schedule

Between February 2026 and July 2026 the site added about 2.5 points a month. At that rate it would finish around November 2028, more than three months after its registered date of June 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2026

31%+13 pts

  • Alba Tower construction site, inspection photo 1, 27 July 2026
  • Alba Tower construction site, inspection photo 2, 27 July 2026
  • Alba Tower construction site, inspection photo 3, 27 July 2026
  • Alba Tower construction site, inspection photo 4, 27 July 2026

24 February 2026

18%+17 pts

  • Alba Tower construction site, inspection photo 1, 24 February 2026
  • Alba Tower construction site, inspection photo 2, 24 February 2026
  • Alba Tower construction site, inspection photo 3, 24 February 2026
  • Alba Tower construction site, inspection photo 4, 24 February 2026

26 June 2025

1.2%+1.2 pts

  • Alba Tower construction site, inspection photo 1, 26 June 2025
  • Alba Tower construction site, inspection photo 2, 26 June 2025
  • Alba Tower construction site, inspection photo 3, 26 June 2025
  • Alba Tower construction site, inspection photo 4, 26 June 2025

23 May 2024

0%

  • Alba Tower construction site, inspection photo 1, 23 May 2024
  • Alba Tower construction site, inspection photo 2, 23 May 2024

All 19 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in Alba Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Alba Tower handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Alba Tower?
Alba Tower was 42% built at the site inspection on 27 July 2026. The site has been inspected 4 times since May 2024. The Land Department took 19 site photos at its inspections.
Is Alba Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Alba Tower?
The registered developer is Century Seven Properties.
Which bank holds the escrow account for Alba Tower?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.