The Grandala construction progress

The Grandala in Jumeirah Garden City is 86% built at the Land Department inspection of August 2026. Developer Palladium Prime Real Estate Development. Completion registered for January 2026.

86%

Built, at the Land Department site inspection of 7 August 2026

8 months past its registered completion date

Completion date (Land Department)
January 2026
Finish at recent pace
October 2026
Construction started
June 2024
Registered with the Land Department
June 2024
Developer
Palladium Prime Real Estate Development
Units
86
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جراندالا
Land Department project number
3046
Land Department site inspections
6

Schedule

The Grandala was registered to complete in January 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 6.3 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 August 2026

86%+23 pts

  • The Grandala construction site, Land Department inspection photo 1, 7 August 2026
  • The Grandala construction site, Land Department inspection photo 2, 7 August 2026
  • The Grandala construction site, Land Department inspection photo 3, 7 August 2026
  • The Grandala construction site, Land Department inspection photo 4, 7 August 2026

5 May 2026

63%+23 pts

  • The Grandala construction site, Land Department inspection photo 1, 5 May 2026
  • The Grandala construction site, Land Department inspection photo 2, 5 May 2026
  • The Grandala construction site, Land Department inspection photo 3, 5 May 2026
  • The Grandala construction site, Land Department inspection photo 4, 5 May 2026

7 January 2026

40%+19 pts

  • The Grandala construction site, Land Department inspection photo 1, 7 January 2026
  • The Grandala construction site, Land Department inspection photo 2, 7 January 2026
  • The Grandala construction site, Land Department inspection photo 3, 7 January 2026
  • The Grandala construction site, Land Department inspection photo 4, 7 January 2026

23 September 2025

20%+5.1 pts

  • The Grandala construction site, Land Department inspection photo 1, 23 September 2025
  • The Grandala construction site, Land Department inspection photo 2, 23 September 2025
  • The Grandala construction site, Land Department inspection photo 3, 23 September 2025
  • The Grandala construction site, Land Department inspection photo 4, 23 September 2025

19 June 2025

15%+15 pts

  • The Grandala construction site, Land Department inspection photo 1, 19 June 2025
  • The Grandala construction site, Land Department inspection photo 2, 19 June 2025
  • The Grandala construction site, Land Department inspection photo 3, 19 June 2025
  • The Grandala construction site, Land Department inspection photo 4, 19 June 2025

9 May 2024

0%

  • The Grandala construction site, Land Department inspection photo 1, 9 May 2024
  • The Grandala construction site, Land Department inspection photo 2, 9 May 2024
  • The Grandala construction site, Land Department inspection photo 3, 9 May 2024

All 44 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Palladium Prime Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Grandala?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Grandala be completed?
The completion date registered with the Dubai Land Department is January 2026. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Grandala is built?
86%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 6 times since May 2024.
Is The Grandala delayed?
Yes. Its registered completion date of January 2026 has passed and the Land Department still lists it as under construction.
Who is building The Grandala?
The registered developer is Palladium Prime Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Grandala?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.