The Grandala construction progress

The Grandala in Jumeirah Garden City was registered to complete in January 2026 and is still under construction. At the last site inspection, in October 2026, it was 91% built. The developer is Palladium Prime Real Estate Development.

91%

Built, at the site inspection of 26 October 2026

10 months past its registered completion date

Registered completion date
January 2026
Finish at recent pace
December 2026
Construction started
June 2024
First registered
June 2024
Developer
Palladium Prime Real Estate Development
Units
86
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جراندالا
Project number
3046
Site inspections
7

Schedule

The Grandala was registered to complete in January 2026, 10 months ago, and is still under construction. Over the last year of inspections it has added about 5.3 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

91%+4.8 pts

  • The Grandala construction site, inspection photo 1, 26 October 2026
  • The Grandala construction site, inspection photo 2, 26 October 2026
  • The Grandala construction site, inspection photo 3, 26 October 2026
  • The Grandala construction site, inspection photo 4, 26 October 2026

7 August 2026

86%+23 pts

  • The Grandala construction site, inspection photo 1, 7 August 2026
  • The Grandala construction site, inspection photo 2, 7 August 2026
  • The Grandala construction site, inspection photo 3, 7 August 2026
  • The Grandala construction site, inspection photo 4, 7 August 2026

5 May 2026

63%+23 pts

  • The Grandala construction site, inspection photo 1, 5 May 2026
  • The Grandala construction site, inspection photo 2, 5 May 2026
  • The Grandala construction site, inspection photo 3, 5 May 2026
  • The Grandala construction site, inspection photo 4, 5 May 2026

7 January 2026

40%+19 pts

  • The Grandala construction site, inspection photo 1, 7 January 2026
  • The Grandala construction site, inspection photo 2, 7 January 2026
  • The Grandala construction site, inspection photo 3, 7 January 2026
  • The Grandala construction site, inspection photo 4, 7 January 2026

23 September 2025

20%+5.1 pts

  • The Grandala construction site, inspection photo 1, 23 September 2025
  • The Grandala construction site, inspection photo 2, 23 September 2025
  • The Grandala construction site, inspection photo 3, 23 September 2025
  • The Grandala construction site, inspection photo 4, 23 September 2025

19 June 2025

15%+15 pts

  • The Grandala construction site, inspection photo 1, 19 June 2025
  • The Grandala construction site, inspection photo 2, 19 June 2025
  • The Grandala construction site, inspection photo 3, 19 June 2025
  • The Grandala construction site, inspection photo 4, 19 June 2025

9 May 2024

0%

  • The Grandala construction site, inspection photo 1, 9 May 2024
  • The Grandala construction site, inspection photo 2, 9 May 2024
  • The Grandala construction site, inspection photo 3, 9 May 2024

All 54 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Palladium Prime Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in The Grandala?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Grandala handover date?
The registered completion date was January 2026, and the register still lists The Grandala as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Grandala?
The Grandala was 91% built at the site inspection on 26 October 2026. The site has been inspected 7 times since May 2024. The Land Department took 54 site photos at its inspections.
Is The Grandala delayed?
Yes. Its registered completion date of January 2026 has passed and the project is still listed as under construction.
Who is building The Grandala?
The registered developer is Palladium Prime Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for The Grandala?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.