Elemental 22 construction progress

Elemental 22 in Jumeirah Garden City is 26% built at the Land Department inspection of July 2026. Developer Elemental Developments. Completion registered for May 2028.

26%

Built, at the Land Department site inspection of 9 July 2026

On pace for its date

Completion date (Land Department)
May 2028
Finish at recent pace
April 2028
Construction started
June 2025
Registered with the Land Department
June 2025
Developer
Elemental Developments
Units
42
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
اليمينتال 22
Land Department project number
3601
Land Department site inspections
3

Schedule

Since April 2026 Elemental 22 has added about 3.6 points a month. That puts 100% around April 2028, within three months of its registered completion date of May 2028.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 July 2026

26%+11 pts

  • Elemental 22 construction site, Land Department inspection photo 1, 9 July 2026
  • Elemental 22 construction site, Land Department inspection photo 2, 9 July 2026
  • Elemental 22 construction site, Land Department inspection photo 3, 9 July 2026
  • Elemental 22 construction site, Land Department inspection photo 4, 9 July 2026

9 April 2026

15%+15 pts

  • Elemental 22 construction site, Land Department inspection photo 1, 9 April 2026
  • Elemental 22 construction site, Land Department inspection photo 2, 9 April 2026
  • Elemental 22 construction site, Land Department inspection photo 3, 9 April 2026

14 May 2025

0%

  • Elemental 22 construction site, Land Department inspection photo 1, 14 May 2025
  • Elemental 22 construction site, Land Department inspection photo 2, 14 May 2025

All 13 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in Elemental 22?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elemental 22 be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Elemental 22 is built?
26%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 3 times since May 2025.
Is Elemental 22 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2028.
Who is building Elemental 22?
The registered developer is Elemental Developments.
Which bank holds the escrow account for Elemental 22?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.