Elemental 22 construction progress
Elemental 22 in Jumeirah Garden City is 26% built at the Land Department inspection of July 2026. Developer Elemental Developments. Completion registered for May 2028.
26%
Built, at the Land Department site inspection of 9 July 2026
On pace for its date
- Completion date (Land Department)
- May 2028
- Finish at recent pace
- April 2028
- Construction started
- June 2025
- Registered with the Land Department
- June 2025
- Developer
- Elemental Developments
- Community
- Jumeirah Garden City
- Units
- 42
- Escrow bank
- National Bank of Ras Al Khaimah
- Name in Arabic
- اليمينتال 22
- Land Department project number
- 3601
- Land Department site inspections
- 3
Schedule
Since April 2026 Elemental 22 has added about 3.6 points a month. That puts 100% around April 2028, within three months of its registered completion date of May 2028.
Site inspections
9 July 2026
26%+11 pts
9 April 2026
15%+15 pts
14 May 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 30% built on average.
Own a unit in Elemental 22?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Elemental 22 be completed?
- The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Elemental 22 is built?
- 26%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 3 times since May 2025.
- Is Elemental 22 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2028.
- Who is building Elemental 22?
- The registered developer is Elemental Developments.
- Which bank holds the escrow account for Elemental 22?
- National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 86%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 31%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)