Elemental 22 construction progress

The registered completion date for Elemental 22 in Jumeirah Garden City is May 2028. At the last site inspection, in November 2026, it was 46% built. The developer is Elemental Developments.

46%

Built, at the site inspection of 4 November 2026

On pace for its date

Registered completion date
May 2028
Finish at recent pace
November 2027
Construction started
June 2025
First registered
June 2025
Developer
Elemental Developments
Units
42
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
اليمينتال 22
Project number
3601
Site inspections
4

Schedule

Since April 2026 Elemental 22 has added about 4.5 points a month. That puts 100% around November 2027, within three months of its registered completion date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 November 2026

46%+20 pts

  • Elemental 22 construction site, inspection photo 1, 4 November 2026
  • Elemental 22 construction site, inspection photo 2, 4 November 2026
  • Elemental 22 construction site, inspection photo 3, 4 November 2026
  • Elemental 22 construction site, inspection photo 4, 4 November 2026

9 July 2026

26%+11 pts

  • Elemental 22 construction site, inspection photo 1, 9 July 2026
  • Elemental 22 construction site, inspection photo 2, 9 July 2026
  • Elemental 22 construction site, inspection photo 3, 9 July 2026
  • Elemental 22 construction site, inspection photo 4, 9 July 2026

9 April 2026

15%+15 pts

  • Elemental 22 construction site, inspection photo 1, 9 April 2026
  • Elemental 22 construction site, inspection photo 2, 9 April 2026
  • Elemental 22 construction site, inspection photo 3, 9 April 2026

14 May 2025

0%

  • Elemental 22 construction site, inspection photo 1, 14 May 2025
  • Elemental 22 construction site, inspection photo 2, 14 May 2025

All 22 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in Elemental 22?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elemental 22 handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elemental 22?
Elemental 22 was 46% built at the site inspection on 4 November 2026. The site has been inspected 4 times since May 2025. The Land Department took 22 site photos at its inspections.
Is Elemental 22 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of May 2028.
Who is building Elemental 22?
The registered developer is Elemental Developments.
Which bank holds the escrow account for Elemental 22?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.