The Elysian construction progress
The registered completion date for The Elysian in Jumeirah Garden City is August 2027. At the last site inspection, in July 2026, it was 4.5% built. The developer is New M F O U R Real Estate Development.
4.5%
Built, at the site inspection of 9 July 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- April 2035
- Construction started
- April 2025
- First registered
- August 2025
- Developer
- New M F O U R Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 84
- Escrow bank
- United Bank Limited
- Name in Arabic
- ذا إليسيان
- Project number
- 3557
- Site inspections
- 3
Schedule
Between February 2026 and July 2026 the site added about 0.9 points a month. At that rate it would finish around April 2035, more than three months after its registered date of August 2027.
Site inspections
9 July 2026
4.5%+4.0 pts
24 February 2026
0.5%+0.5 pts
24 February 2025
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Own a unit in The Elysian?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Elysian handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Elysian?
- The Elysian was 4.5% built at the site inspection on 9 July 2026. The site has been inspected 3 times since February 2025. The Land Department took 11 site photos at its inspections.
- Is The Elysian delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building The Elysian?
- The registered developer is New M F O U R Real Estate Development.
- Which bank holds the escrow account for The Elysian?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.