The Elysian construction progress

The Elysian in Jumeirah Garden City is 4.5% built at the Land Department inspection of July 2026. Developer New M F O U R Real Estate Development. Completion registered for August 2027.

4.5%

Built, at the Land Department site inspection of 9 July 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
April 2035
Construction started
April 2025
Registered with the Land Department
August 2025
Developer
New M F O U R Real Estate Development
Units
84
Escrow bank
United Bank Limited
Name in Arabic
ذا إليسيان
Land Department project number
3557
Land Department site inspections
3

Schedule

Between February 2026 and July 2026 the site added about 0.9 points a month. At that rate it would finish around April 2035, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 July 2026

4.5%+4.0 pts

  • The Elysian construction site, Land Department inspection photo 1, 9 July 2026
  • The Elysian construction site, Land Department inspection photo 2, 9 July 2026
  • The Elysian construction site, Land Department inspection photo 3, 9 July 2026
  • The Elysian construction site, Land Department inspection photo 4, 9 July 2026

24 February 2026

0.5%+0.5 pts

  • The Elysian construction site, Land Department inspection photo 1, 24 February 2026
  • The Elysian construction site, Land Department inspection photo 2, 24 February 2026
  • The Elysian construction site, Land Department inspection photo 3, 24 February 2026

24 February 2025

0%

  • The Elysian construction site, Land Department inspection photo 1, 24 February 2025
  • The Elysian construction site, Land Department inspection photo 2, 24 February 2025

All 11 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Own a unit in The Elysian?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Elysian be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around April 2035. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Elysian is built?
4.5%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 3 times since February 2025.
Is The Elysian delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building The Elysian?
The registered developer is New M F O U R Real Estate Development.
Which bank holds the escrow account for The Elysian?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.