Jad 288 construction progress

The registered completion date for Jad 288 in Jumeirah Garden City is December 2027. At the last site inspection, in July 2026, it was 1.9% built. The developer is Jad Global Real Estate Development.

1.9%

Built, at the site inspection of 27 July 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
June 2073
Construction started
December 2025
First registered
October 2025
Units
222
Escrow bank
Dubai Islamic Bank
Name in Arabic
جاد 288
Project number
3798
Site inspections
2

Schedule

Between September 2025 and July 2026 the site added about 0.2 points a month. At that rate it would finish around June 2073, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2026

1.9%+1.9 pts

  • Jad 288 construction site, inspection photo 1, 27 July 2026
  • Jad 288 construction site, inspection photo 2, 27 July 2026
  • Jad 288 construction site, inspection photo 3, 27 July 2026
  • Jad 288 construction site, inspection photo 4, 27 July 2026

2 September 2025

0%

  • Jad 288 construction site, inspection photo 1, 2 September 2025
  • Jad 288 construction site, inspection photo 2, 2 September 2025

All 7 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Jad Global Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Jad 288?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Jad 288 handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2073. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Jad 288?
Jad 288 was 1.9% built at the site inspection on 27 July 2026. The site has been inspected 2 times since September 2025. The Land Department took 7 site photos at its inspections.
Is Jad 288 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Jad 288?
The registered developer is Jad Global Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Jad 288?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.