Stamn One construction progress
Stamn One in Jumeirah Garden City was registered to complete in October 2026 and is still under construction. At the last site inspection, in August 2026, it was 42% built. The developer is Stamn Real Estate Development.
42%
Built, at the site inspection of 25 August 2026
1 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- October 2027
- Construction started
- February 2025
- First registered
- December 2024
- Developer
- Stamn Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 77
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ستامن وان
- Project number
- 3243
- Site inspections
- 5
Schedule
Stamn One was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.1 points a month. Kept at that rate, the site would reach 100% around October 2027.
Site inspections
25 August 2026
42%+11 pts
11 June 2026
31%+14 pts
24 February 2026
17%+12 pts
20 November 2025
4.8%+4.8 pts
22 October 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Stamn Real Estate Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Stamn One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Stamn One handover date?
- The registered completion date was October 2026, and the register still lists Stamn One as under construction. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Stamn One?
- Stamn One was 42% built at the site inspection on 25 August 2026. The site has been inspected 5 times since October 2024. The Land Department took 33 site photos at its inspections.
- Is Stamn One delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Stamn One?
- The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Stamn One?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Stamn YuniAlso by Stamn Real Estate Development. 21%, Due March 2027.
- Nautis ResidencesAlso by Stamn Real Estate Development. 0.9%, Due August 2027.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.