Stamn One construction progress

Stamn One in Jumeirah Garden City is 42% built at the Land Department inspection of August 2026. Developer Stamn Real Estate Development. Completion registered for October 2026.

42%

Built, at the Land Department site inspection of 25 August 2026

Running behind its date

Completion date (Land Department)
October 2026
Finish at recent pace
October 2027
Construction started
February 2025
Registered with the Land Department
December 2024
Units
77
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ستامن وان
Land Department project number
3243
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 4.1 points a month. At that rate it would finish around October 2027, more than three months after the October 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 August 2026

42%+11 pts

  • Stamn One construction site, Land Department inspection photo 1, 25 August 2026
  • Stamn One construction site, Land Department inspection photo 2, 25 August 2026
  • Stamn One construction site, Land Department inspection photo 3, 25 August 2026
  • Stamn One construction site, Land Department inspection photo 4, 25 August 2026

11 June 2026

31%+14 pts

  • Stamn One construction site, Land Department inspection photo 1, 11 June 2026
  • Stamn One construction site, Land Department inspection photo 2, 11 June 2026
  • Stamn One construction site, Land Department inspection photo 3, 11 June 2026
  • Stamn One construction site, Land Department inspection photo 4, 11 June 2026

24 February 2026

17%+12 pts

  • Stamn One construction site, Land Department inspection photo 1, 24 February 2026
  • Stamn One construction site, Land Department inspection photo 2, 24 February 2026
  • Stamn One construction site, Land Department inspection photo 3, 24 February 2026
  • Stamn One construction site, Land Department inspection photo 4, 24 February 2026

20 November 2025

4.8%+4.8 pts

  • Stamn One construction site, Land Department inspection photo 1, 20 November 2025
  • Stamn One construction site, Land Department inspection photo 2, 20 November 2025
  • Stamn One construction site, Land Department inspection photo 3, 20 November 2025
  • Stamn One construction site, Land Department inspection photo 4, 20 November 2025

22 October 2024

0%

  • Stamn One construction site, Land Department inspection photo 1, 22 October 2024
  • Stamn One construction site, Land Department inspection photo 2, 22 October 2024

All 33 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Stamn Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Stamn One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Stamn One be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Stamn One is built?
42%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 5 times since October 2024.
Is Stamn One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2026.
Who is building Stamn One?
The registered developer is Stamn Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Stamn One?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.