Mayfair Gardens By Majid construction progress

Mayfair Gardens By Majid in Jumeirah Garden City was registered to complete in August 2026 and is still under construction. At the last site inspection, in August 2026, it was 70% built. The developer is Majid Developments.

70%

Built, at the site inspection of 20 August 2026

3 months past its registered completion date

Registered completion date
August 2026
Finish at recent pace
February 2027
Construction started
August 2024
First registered
September 2024
Units
64
Escrow bank
Emirates NBD
Name in Arabic
حدائق مايفاير مجيد
Project number
3207
Site inspections
6

Schedule

Mayfair Gardens By Majid was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 5.1 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 August 2026

70%+20 pts

  • Mayfair Gardens By Majid construction site, inspection photo 1, 20 August 2026
  • Mayfair Gardens By Majid construction site, inspection photo 2, 20 August 2026
  • Mayfair Gardens By Majid construction site, inspection photo 3, 20 August 2026
  • Mayfair Gardens By Majid construction site, inspection photo 4, 20 August 2026

18 May 2026

50%+20 pts

  • Mayfair Gardens By Majid construction site, inspection photo 1, 18 May 2026
  • Mayfair Gardens By Majid construction site, inspection photo 2, 18 May 2026
  • Mayfair Gardens By Majid construction site, inspection photo 3, 18 May 2026
  • Mayfair Gardens By Majid construction site, inspection photo 4, 18 May 2026

26 January 2026

30%+13 pts

  • Mayfair Gardens By Majid construction site, inspection photo 1, 26 January 2026
  • Mayfair Gardens By Majid construction site, inspection photo 2, 26 January 2026
  • Mayfair Gardens By Majid construction site, inspection photo 3, 26 January 2026
  • Mayfair Gardens By Majid construction site, inspection photo 4, 26 January 2026

13 October 2025

18%+16 pts

  • Mayfair Gardens By Majid construction site, inspection photo 1, 13 October 2025
  • Mayfair Gardens By Majid construction site, inspection photo 2, 13 October 2025
  • Mayfair Gardens By Majid construction site, inspection photo 3, 13 October 2025
  • Mayfair Gardens By Majid construction site, inspection photo 4, 13 October 2025

22 May 2025

1.7%+1.7 pts

  • Mayfair Gardens By Majid construction site, inspection photo 1, 22 May 2025
  • Mayfair Gardens By Majid construction site, inspection photo 2, 22 May 2025
  • Mayfair Gardens By Majid construction site, inspection photo 3, 22 May 2025
  • Mayfair Gardens By Majid construction site, inspection photo 4, 22 May 2025

31 July 2024

0%

  • Mayfair Gardens By Majid construction site, inspection photo 1, 31 July 2024
  • Mayfair Gardens By Majid construction site, inspection photo 2, 31 July 2024

All 40 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Majid Developments has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Mayfair Gardens By Majid?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mayfair Gardens By Majid handover date?
The registered completion date was August 2026, and the register still lists Mayfair Gardens By Majid as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mayfair Gardens By Majid?
Mayfair Gardens By Majid was 70% built at the site inspection on 20 August 2026. The site has been inspected 6 times since July 2024. The Land Department took 40 site photos at its inspections.
Is Mayfair Gardens By Majid delayed?
Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
Who is building Mayfair Gardens By Majid?
The registered developer is Majid Developments. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Mayfair Gardens By Majid?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.