Mayfair Gardens By Majid construction progress
Mayfair Gardens By Majid in Jumeirah Garden City was registered to complete in August 2026 and is still under construction. At the last site inspection, in August 2026, it was 70% built. The developer is Majid Developments.
70%
Built, at the site inspection of 20 August 2026
3 months past its registered completion date
- Registered completion date
- August 2026
- Finish at recent pace
- February 2027
- Construction started
- August 2024
- First registered
- September 2024
- Developer
- Majid Developments
- Community
- Jumeirah Garden City
- Units
- 64
- Escrow bank
- Emirates NBD
- Name in Arabic
- حدائق مايفاير مجيد
- Project number
- 3207
- Site inspections
- 6
Schedule
Mayfair Gardens By Majid was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 5.1 points a month. Kept at that rate, the site would reach 100% around February 2027.
Site inspections
20 August 2026
70%+20 pts
18 May 2026
50%+20 pts
26 January 2026
30%+13 pts
13 October 2025
18%+16 pts
22 May 2025
1.7%+1.7 pts
31 July 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Majid Developments has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Mayfair Gardens By Majid?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mayfair Gardens By Majid handover date?
- The registered completion date was August 2026, and the register still lists Mayfair Gardens By Majid as under construction. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mayfair Gardens By Majid?
- Mayfair Gardens By Majid was 70% built at the site inspection on 20 August 2026. The site has been inspected 6 times since July 2024. The Land Department took 40 site photos at its inspections.
- Is Mayfair Gardens By Majid delayed?
- Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
- Who is building Mayfair Gardens By Majid?
- The registered developer is Majid Developments. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Mayfair Gardens By Majid?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Arlington Park By MajidAlso by Majid Developments. 5.7%, Due December 2027.
- Arlington Park II By MajidAlso by Majid Developments. 0%, Due April 2028.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- Trillium HeightsNearby in Jumeirah Garden City. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.












.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)