Evergrin House construction progress

Evergrin House in Jumeirah Garden City was registered to complete in June 2026 and is still under construction. At the last site inspection, in July 2026, it was 55% built. The developer is Obj1 Real Estate Development.

55%

Built, at the site inspection of 9 July 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
April 2030
Construction started
November 2024
First registered
October 2024
Units
219
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
أيفرجرين هاوس
Project number
3274
Site inspections
4

Schedule

Evergrin House was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around April 2030.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 July 2026

55%+6.6 pts

  • Evergrin House construction site, inspection photo 1, 9 July 2026
  • Evergrin House construction site, inspection photo 2, 9 July 2026
  • Evergrin House construction site, inspection photo 3, 9 July 2026
  • Evergrin House construction site, inspection photo 4, 9 July 2026

23 December 2025

48%+34 pts

  • Evergrin House construction site, inspection photo 1, 23 December 2025
  • Evergrin House construction site, inspection photo 2, 23 December 2025
  • Evergrin House construction site, inspection photo 3, 23 December 2025
  • Evergrin House construction site, inspection photo 4, 23 December 2025

9 June 2025

14%+14 pts

  • Evergrin House construction site, inspection photo 1, 9 June 2025
  • Evergrin House construction site, inspection photo 2, 9 June 2025
  • Evergrin House construction site, inspection photo 3, 9 June 2025
  • Evergrin House construction site, inspection photo 4, 9 June 2025

15 October 2024

0%

  • Evergrin House construction site, inspection photo 1, 15 October 2024
  • Evergrin House construction site, inspection photo 2, 15 October 2024

All 28 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Evergrin House?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Evergrin House handover date?
The registered completion date was June 2026, and the register still lists Evergrin House as under construction. At the pace of its recent inspections the site would reach 100% around April 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Evergrin House?
Evergrin House was 55% built at the site inspection on 9 July 2026. The site has been inspected 4 times since October 2024. The Land Department took 28 site photos at its inspections.
Is Evergrin House delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Evergrin House?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Evergrin House?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.