Evergrin House construction progress

Evergrin House in Jumeirah Garden City is 55% built at the Land Department inspection of July 2026. Developer Obj1 Real Estate Development. Completion registered for June 2026.

55%

Built, at the Land Department site inspection of 9 July 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
April 2030
Construction started
November 2024
Registered with the Land Department
October 2024
Units
219
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
أيفرجرين هاوس
Land Department project number
3274
Land Department site inspections
4

Schedule

Evergrin House was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around April 2030.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 July 2026

55%+6.6 pts

  • Evergrin House construction site, Land Department inspection photo 1, 9 July 2026
  • Evergrin House construction site, Land Department inspection photo 2, 9 July 2026
  • Evergrin House construction site, Land Department inspection photo 3, 9 July 2026
  • Evergrin House construction site, Land Department inspection photo 4, 9 July 2026

23 December 2025

48%+34 pts

  • Evergrin House construction site, Land Department inspection photo 1, 23 December 2025
  • Evergrin House construction site, Land Department inspection photo 2, 23 December 2025
  • Evergrin House construction site, Land Department inspection photo 3, 23 December 2025
  • Evergrin House construction site, Land Department inspection photo 4, 23 December 2025

9 June 2025

14%+14 pts

  • Evergrin House construction site, Land Department inspection photo 1, 9 June 2025
  • Evergrin House construction site, Land Department inspection photo 2, 9 June 2025
  • Evergrin House construction site, Land Department inspection photo 3, 9 June 2025
  • Evergrin House construction site, Land Department inspection photo 4, 9 June 2025

15 October 2024

0%

  • Evergrin House construction site, Land Department inspection photo 1, 15 October 2024
  • Evergrin House construction site, Land Department inspection photo 2, 15 October 2024

All 28 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Obj1 Real Estate Development has 14 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Evergrin House?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Evergrin House be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around April 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Evergrin House is built?
55%, measured at the Land Department site inspection on 9 July 2026. The Land Department engineers have inspected the site 4 times since October 2024.
Is Evergrin House delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Evergrin House?
The registered developer is Obj1 Real Estate Development. It has 13 other projects under construction in Dubai.
Which bank holds the escrow account for Evergrin House?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.