Trillium Heights construction progress

Trillium Heights in Jumeirah Garden City was registered to complete in December 2025 and is still under construction. At the last site inspection, in June 2026, it was 62% built. The developer is Grenorbit Real Estate Development.

62%

Built, at the site inspection of 16 June 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
March 2027
Construction started
June 2024
First registered
September 2024
Developer
Grenorbit Real Estate Development
Units
56
Escrow bank
First Abu Dhabi Bank
Name in Arabic
تريليوم هايتس
Project number
3075
Site inspections
4

Schedule

Trillium Heights was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 June 2026

62%+29 pts

  • Trillium Heights construction site, inspection photo 1, 16 June 2026
  • Trillium Heights construction site, inspection photo 2, 16 June 2026
  • Trillium Heights construction site, inspection photo 3, 16 June 2026
  • Trillium Heights construction site, inspection photo 4, 16 June 2026

17 December 2025

33%+23 pts

  • Trillium Heights construction site, inspection photo 1, 17 December 2025
  • Trillium Heights construction site, inspection photo 2, 17 December 2025
  • Trillium Heights construction site, inspection photo 3, 17 December 2025
  • Trillium Heights construction site, inspection photo 4, 17 December 2025

20 June 2025

9.6%+9.6 pts

  • Trillium Heights construction site, inspection photo 1, 20 June 2025
  • Trillium Heights construction site, inspection photo 2, 20 June 2025
  • Trillium Heights construction site, inspection photo 3, 20 June 2025
  • Trillium Heights construction site, inspection photo 4, 20 June 2025

30 May 2024

0%

  • Trillium Heights construction site, inspection photo 1, 30 May 2024
  • Trillium Heights construction site, inspection photo 2, 30 May 2024

All 21 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 34% built on average.

Own a unit in Trillium Heights?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Trillium Heights handover date?
The registered completion date was December 2025, and the register still lists Trillium Heights as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Trillium Heights?
Trillium Heights was 62% built at the site inspection on 16 June 2026. The site has been inspected 4 times since May 2024. The Land Department took 21 site photos at its inspections.
Is Trillium Heights delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Trillium Heights?
The registered developer is Grenorbit Real Estate Development.
Which bank holds the escrow account for Trillium Heights?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.