Trillium Heights construction progress
Trillium Heights in Jumeirah Garden City is 62% built at the Land Department inspection of June 2026. Developer Grenorbit Real Estate Development. Completion registered for December 2025.
62%
Built, at the Land Department site inspection of 16 June 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- March 2027
- Construction started
- June 2024
- Registered with the Land Department
- September 2024
- Developer
- Grenorbit Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 56
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- تريليوم هايتس
- Land Department project number
- 3075
- Land Department site inspections
- 4
Schedule
Trillium Heights was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around March 2027.
Site inspections
16 June 2026
62%+29 pts
17 December 2025
33%+23 pts
20 June 2025
9.6%+9.6 pts
30 May 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 30% built on average. Trillium Heights is ahead of that average.
Own a unit in Trillium Heights?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Trillium Heights be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Trillium Heights is built?
- 62%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 4 times since May 2024.
- Is Trillium Heights delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Trillium Heights?
- The registered developer is Grenorbit Real Estate Development.
- Which bank holds the escrow account for Trillium Heights?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 86%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 31%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- 161 Jumeirah LaneNearby in Jumeirah Garden City. 70%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)