Trillium Heights construction progress

Trillium Heights in Jumeirah Garden City is 62% built at the Land Department inspection of June 2026. Developer Grenorbit Real Estate Development. Completion registered for December 2025.

62%

Built, at the Land Department site inspection of 16 June 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
March 2027
Construction started
June 2024
Registered with the Land Department
September 2024
Developer
Grenorbit Real Estate Development
Units
56
Escrow bank
First Abu Dhabi Bank
Name in Arabic
تريليوم هايتس
Land Department project number
3075
Land Department site inspections
4

Schedule

Trillium Heights was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around March 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 June 2026

62%+29 pts

  • Trillium Heights construction site, Land Department inspection photo 1, 16 June 2026
  • Trillium Heights construction site, Land Department inspection photo 2, 16 June 2026
  • Trillium Heights construction site, Land Department inspection photo 3, 16 June 2026
  • Trillium Heights construction site, Land Department inspection photo 4, 16 June 2026

17 December 2025

33%+23 pts

  • Trillium Heights construction site, Land Department inspection photo 1, 17 December 2025
  • Trillium Heights construction site, Land Department inspection photo 2, 17 December 2025
  • Trillium Heights construction site, Land Department inspection photo 3, 17 December 2025
  • Trillium Heights construction site, Land Department inspection photo 4, 17 December 2025

20 June 2025

9.6%+9.6 pts

  • Trillium Heights construction site, Land Department inspection photo 1, 20 June 2025
  • Trillium Heights construction site, Land Department inspection photo 2, 20 June 2025
  • Trillium Heights construction site, Land Department inspection photo 3, 20 June 2025
  • Trillium Heights construction site, Land Department inspection photo 4, 20 June 2025

30 May 2024

0%

  • Trillium Heights construction site, Land Department inspection photo 1, 30 May 2024
  • Trillium Heights construction site, Land Department inspection photo 2, 30 May 2024

All 21 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average. Trillium Heights is ahead of that average.

Own a unit in Trillium Heights?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Trillium Heights be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Trillium Heights is built?
62%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 4 times since May 2024.
Is Trillium Heights delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Trillium Heights?
The registered developer is Grenorbit Real Estate Development.
Which bank holds the escrow account for Trillium Heights?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.