Trillium Heights construction progress
Trillium Heights in Jumeirah Garden City was registered to complete in December 2025 and is still under construction. At the last site inspection, in June 2026, it was 62% built. The developer is Grenorbit Real Estate Development.
62%
Built, at the site inspection of 16 June 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- March 2027
- Construction started
- June 2024
- First registered
- September 2024
- Developer
- Grenorbit Real Estate Development
- Community
- Jumeirah Garden City
- Units
- 56
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- تريليوم هايتس
- Project number
- 3075
- Site inspections
- 4
Schedule
Trillium Heights was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around March 2027.
Site inspections
16 June 2026
62%+29 pts
17 December 2025
33%+23 pts
20 June 2025
9.6%+9.6 pts
30 May 2024
0%
Context
Jumeirah Garden City has 27 projects under construction, 34% built on average.
Own a unit in Trillium Heights?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Trillium Heights handover date?
- The registered completion date was December 2025, and the register still lists Trillium Heights as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Trillium Heights?
- Trillium Heights was 62% built at the site inspection on 16 June 2026. The site has been inspected 4 times since May 2024. The Land Department took 21 site photos at its inspections.
- Is Trillium Heights delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Trillium Heights?
- The registered developer is Grenorbit Real Estate Development.
- Which bank holds the escrow account for Trillium Heights?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The GrandalaNearby in Jumeirah Garden City. 91%, Due January 2026, passed.
- Alba TowerNearby in Jumeirah Garden City. 42%, Due June 2028.
- Jardin AstralNearby in Jumeirah Garden City. 45%, Due August 2026, passed.
- 161 Jumeirah LaneNearby in Jumeirah Garden City. 70%, Due March 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)